One phase, several names
The instructor grouped early initiation and planning work under the pre-project phase, also called front-end loading (FEL). Its purpose is to progressively justify whether the sponsor's idea makes sense before full authorization and execution. In the humanitarian sector, a comparable early activity may be described as a needs assessment.
At the start, the project is only an idea
The instructor described the project sponsor as the person with the idea and a vested interest in seeing it move forward. That sponsor takes the idea to a governance board. At this early point, the proposed project may be represented by only a few pages of high-level information — the idea, expected returns or value at a high level, and possible project options. It is not yet treated as a fully authorized execution project.
What the front end is trying to produce
The pre-project phase exists to build enough evidence for a decision, not to begin delivery.
- Reduce uncertainty before major commitment.
- Test feasibility and evaluate value.
- Compare options and improve definition.
- Understand resources and identify important stakeholders.
- Estimate time and cost, and assess risk.
- Create enough evidence for an authorization decision.
The key principle
Front-end loading should make the project more executable and reduce the risk profile before execution begins. Prior Module 1 work adds a consequence worth noting: if an organization starts the year with many project ideas and adds none, stage-gated filtering should normally leave fewer active projects. The purpose of the front end is not to push every idea into execution.
How pre-project work is paid for
A participant asked the obvious question: if the project does not exist yet, where does the money for the people working on it come from? The instructor explained that the organization approves a fund specifically for that phase, expressed as a number of hours the team can use. From an accounting perspective those costs are expensed, not capitalized. If the project is later authorized, the money already spent becomes part of the project budget; if it is not, it stays an organizational expense.
Not a universal ruleThe session used accounting words loosely here — expensed, sunk, and part of the project budget all appear in the same answer. Take the broad distinction, not a precise accounting treatment.
What the front end costs
Asked what share of total project cost the whole initiation and planning period takes, a participant guessed less than 5%. The instructor raised it: around 8–11% of total project cost. That is a meaningful amount to spend on an idea that may still be stopped — which is exactly why the front end is itself gated.
Not a universal ruleThe 8–11% figure is a statement made in this session, not a validated universal standard. Do not carry it into another organization or project type as a benchmark without supporting course material.