Assess, select, and define

Follow the three front-end subphases that turn an idea into a decision-ready proposal.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

Assessment asks: is this worth pursuing?

Assessment is the first feasibility-focused stage. It explores whether the opportunity is viable and worthwhile, including economic, social, environmental, and strategic considerations. Some organizations maintain a portfolio of possibilities before assessment; others add a proposal after an initial assessment. In either case, this is investigation, not yet a promise to deliver.

Selection turns options into a preferred concept

Once a business case appears viable, the team compares alternatives and begins to shape a preferred scope. Representatives from relevant functions should participate: business, operations, legal, safety, security, interfaces, stakeholders, engineering, procurement, or others appropriate to the project. The aim is to avoid a narrow solution chosen by only one perspective.

Definition makes the chosen concept decision-ready

The team prepares a project charter to formally frame the project under sponsor guidance. It then plans the pre-project work itself: which studies, approvals, procurement strategy, resources, and priorities are needed before a final authorization request can be made. In the definition phase, risk analysis, detailed planning, schedules, safety, and control procedures come together in an authorization package.

Use the right question at each point

Assessment asks whether the opportunity merits further work. Selection asks which viable concept best fits the need. Definition asks whether the preferred option is sufficiently understood, planned, and controlled to authorize. Mixing these questions leads to teams trying to plan a project that has not yet earned a decision to proceed.

Study explanation based on the supplied Week 1: The Front End source deck. Open the source notes above for slide-level traceability.