A home for project governance
A Project Management Office (PMO) is a department within an organization that provides project governance or ensures compliance with it. Its core job is to oversee and standardize how projects are managed, so that practices, methods, and frameworks are consistent and projects stay aligned with strategy. Depending on the organization’s needs and maturity, a PMO takes one of three forms, each with a different level of authority.
Supportive: a resource center
A supportive PMO provides the policies, methodologies, templates, and lessons learned that project teams use. It acts as a central repository of project-management knowledge and aims to improve current and future performance. Because it advises rather than directs, it exercises a low level of control over projects.
Controlling: support plus compliance
A controlling PMO offers guidance and tools and also enforces standards. It trains people in project management and project-management software, helps teams use specific tools, and ensures projects follow organizational policies, often through audits, reviews, and required documentation, approvals, or checkpoints before a team can move forward. Its control is moderate.
Directive: the PMO runs the projects
A directive PMO takes full control. It assigns project managers directly, project managers report to it, and it is accountable for project outcomes: scope, schedule, and budget. Rather than advising or monitoring, it actively manages all projects or particular categories, typically those with high complexity, strategic importance, or significant investment.
- Supportive, least control: advises and equips.
- Controlling, medium control: monitors and enforces compliance.
- Directive, most control: manages projects and owns their outcomes.
What else a PMO does
Beyond standardizing practice, a PMO can play a wide range of strategic and operational roles. The source lists thirteen; grouped, they look like this.
- Across the organization: manage interdependencies among projects, programs, and portfolios; analyze project information to judge whether strategic objectives are being met; prioritize projects.
- Resources and decisions: help provide resources; recommend terminating projects when appropriate; sit on change control boards; act as a stakeholder.
- Standards and knowledge: monitor compliance with processes; collect lessons learned into a repository; provide templates such as work breakdown structures, user stories, and communication management plans.
- Governance and communication: provide guidance and project governance; centralize communication about projects; engage most heavily during initiation.