The case at a glance
The applied case is a proposed charter for a book donation and distribution initiative called 2,000 Books for Learning. It will procure and distribute 2,000 usable, educationally appropriate books to four primary schools in one rural district in Cambodia, Southeast Asia. A local NGO will coordinate delivery using books already available in-country. The work is to finish within six weeks of written authorization, not by a calendar date, and within a cash ceiling of USD 9,200.
- The sponsor is the client funding representative. The charter proposes its author as Project Manager, an appointment the sponsor's signature would make.
- The charter is proposed and unsigned. Its signature lines are blank because it is an academic charter.
Read with careCambodia, the NGO, the four schools, the suppliers, the prices and the sponsor are planning assumptions for an academic scenario. None of them is a real, verified commitment, and no field work was done.
The question a charter must answer
The companion guide frames the whole task with one question: can the sponsor understand what is being authorized, how success will be judged, who can make decisions, and what uncertainties could prevent success? Week 2 defined what the project should achieve. Week 3 turns that definition into a document a sponsor could use to authorize the project: understandable, bounded and governable. It is not a longer objectives list, and it is not a detailed delivery plan.
Where the charter answers the brief
The assignment brief named the sections it required. Each one maps to a numbered section of the charter.
| Brief requirement | Where the charter answers it |
|---|---|
| Project title | Opening title and Section 1: the book initiative and its purpose |
| Project scope | Section 2: included deliverables and explicit exclusions |
| SMART objectives | Section 3: six measurable objectives with deadlines and evidence |
| Project Manager authority | Section 6: decision limits, escalation and justification |
| Top three risks | Section 7: uncertain events, classification, impact and rationale |
| Stakeholders | Section 8: roles, importance, power, interest and engagement |
| Professional, complete charter | Sections 4, 5 and 9: assumptions, budget, milestones, acceptance and authorization |
Why the extra sections belong
The charter also carries assumptions, a budget, milestones, acceptance and authorization, which the brief did not name. They belong because the deck lists assumptions and constraints, a high-level timeline and budget, and approval as charter components. They complete the logic of authorization without turning the charter into an execution manual. The cross-walk below matches each of the deck's ten components to its place in the charter.
| Deck component | Charter section |
|---|---|
| Project title and description | Title block and Section 1 |
| Business need or problem statement | Section 1: limited access to suitable reading materials |
| Objectives and success criteria | Section 3, with acceptance in Section 9 |
| Scope overview | Section 2 |
| Assumptions and constraints | Section 4 |
| High-level timeline and budget | Section 5 |
| Stakeholder list | Section 8 |
| Roles and responsibilities | Section 6 for authority and Section 8 for roles |
| Risks and dependencies | Section 7, with dependencies in Section 4 |
| Approval and sign-off | Section 9 |
Why the Week 2 project was kept
The brief says this assignment builds directly on Week 2, so replacing the project would weaken compliance unless the instructor approved a change. The charter keeps the Week 2 baseline and develops each part of it.
| Week 2 baseline retained | How Week 3 develops it |
|---|---|
| 2,000 books; four primary schools; one rural district in Cambodia | Defines the boundary and requires reconciled school-level receipts |
| Books already available in-country; local NGO delivery | Keeps international shipping out of scope and prioritizes domestic logistics |
| Six weeks from written authorization | Adds milestones, prerequisites and a controlled completion boundary |
| USD 9,200 maximum cash expenditure | Retains the USD 8,000 base plus USD 1,200 contingency and adds spending authority |
| Approved book list and allocation in Week 1 | Makes documented recipient agreement a prerequisite to purchasing |
| Complete, legible books without water damage | Defines 100% conformity for books counted at acceptance |
| Inventories, custodians, pupil access and client acceptance by Week 6 | Identifies handover evidence and separates school receipt from sponsor closure |
| At least 80% carton reuse or recovery | Adds a denominator and a requirement for recorded confirmation |
Read with careThe Week 2 baseline was recovered from a drafting conversation. It was not compared with the submitted Week 2 document, so read it as the recovered draft rather than a checked final version.
What was not assumed
Continuity does not mean inventing detail. The guide is explicit about three things the charter does not assume.
- No equal split of 500 books per school. The allocation must total 2,000 and follow validated needs.
- The brief's illustrative objective, three schools in six months for GBP 50,000, shows the form of a measurable objective. It is not this project's baseline.
- No real school, NGO, supplier, survey, quotation or sponsor approval was invented.