Project Management · Module 3 applied case practice
Decide within the limits. Escalate beyond them.
These decisions test the proposed charter's own rules: its delegated limits, its scope boundary, and its acceptance evidence. They practise project reasoning on an academic case; they are not a replacement for organizational authority, professional judgment, or a real project's formal controls.
Decide within the charter
The USD 200 reroute
A road closure forces the domestic carrier onto a longer route, adding USD 200. It is an in-scope response, no contingency has been released yet, the transport package will stay under USD 1,000, and the forecast total stays within USD 9,200.
What may the Project Manager do?
Check your understanding
Explain the charter without memorizing it.
Choose the strongest answer from the proposed charter and the course distinctions behind it.