01 Why does the deck call the project charter a process rather than a milestone?Because it is signed at the end of the project. Because developing it covers the planning work of the definition phase and rests on the assumptions and constraints found there. Because it is updated at every project milestone. Because it replaces the project plan.
02 What does the deck say happens only after the charter is signed?Stakeholders are first identified. Detailed planning begins, and additional time and money are committed. The business case is written. The sponsor is chosen.
03 Which pairing matches the deck's comparison of a charter and a plan?Charter: detailed and owned by the project manager; plan: high-level and owned by the sponsor. Charter: initiation, authorizes the project, owned by the sponsor; plan: planning, guides execution, owned by the project manager. Charter: defines the detailed WBS; plan: outlines the general scope. They are the same document written at different dates.
04 Which statement reflects the deck's best practices for writing a charter?The more complex the project, the more detailed the charter must be. The more complex the project, the simpler the charter needs to be. A charter should describe the scope in full detail. A charter only needs the sponsor to agree with it.
05 Who creates the project charter, and who approves it?The sponsor creates it and the project manager approves it. The project manager creates it, and the sponsor, representing the business investing the money, approves it. The PMO creates and approves it. The team creates it and key stakeholders approve it.
06 When the deck calls the charter a guardrail, what does it mean?It keeps the team focused on the original goals. It sets boundaries on scope, resources, and objectives that help prevent scope creep. It protects the project manager from difficult stakeholders. It guarantees the budget will not change.
07 Which of these is an internal risk in the deck's classification?A change in regulations. A new competitor entering the market. Team turnover. A natural disaster.
08 What is the main benefit of Delphi's anonymity, according to the deck?It is faster than interviews. Ideas can be generated without fear of ridicule. It removes the need for a moderator. It produces quantitative risk scores.
09 On the deck's power/interest grid, how should a high-power, high-interest stakeholder be treated?Keep informed. Maintain interest. Regularly engage. Actively consult.
10 In the salience model, which stakeholders receive the highest priority?Stakeholders with power only. Stakeholders with legitimacy and urgency. Definitive stakeholders, who have legitimacy, power, and urgency. Discretionary stakeholders.
11 In the deck's example delegation table, a schedule change would cause a three-week delay. What happens?The project manager approves it, because schedule changes are delegated. The functional manager decides. It needs sponsor approval, because it exceeds the two-week limit. The procurement lead decides.
12 How does a RACI chart differ from the delegation of authority?RACI shows who decides; the delegation of authority shows who does the work. RACI maps who is responsible, accountable, consulted, and informed; the delegation of authority defines who can decide and under what conditions. They are two names for the same table. RACI is only used on humanitarian projects.