01 In version 2 of the charter, who may release contingency?Only the sponsor, for every release. The project manager, up to USD 300 per risk event. The project manager, up to USD 600 in total. Finance, once a quotation is received.
02 The manager signs a USD 600 order with a supplier, then needs a second USD 600 order from the same supplier. What does the charter require?Nothing further: each order is below USD 1,000. Sponsor approval, because the aggregate with that supplier reaches USD 1,200. Splitting the second order into two smaller ones. A new quotation round for the second order only.
03 Why did delivery and handover move to the end of Week 5 in version 2?To shorten the project to five weeks. Because the sponsor asked for earlier delivery. To keep Week 6 for verification, reconciliation and acceptance rather than routine late delivery. Because transport was expected to fail.
04 A quotation lifts the forecast total to USD 8,400 against a USD 9,200 ceiling. What does the guide say happens?Nothing: the forecast is below the ceiling. The book target is reduced to protect the budget. Finance reallocates from the packaging allowance. The extra USD 400 is contingency, so it needs an authorized release.
05 What role does the charter give the NGO in the contracting structure?It becomes the purchasing principal for the project. It coordinates and verifies evidence, and cannot bind the client beyond an explicit delegation. It signs supplier contracts on the client's behalf. It holds the handover agreements with the schools.
06 Why does the charter evaluate more than price when selecting a supplier?Because procurement law requires it in Cambodia. Because fixed-price contracts forbid price comparison. Because the sponsor prefers established suppliers. Because a cheap book that fails the agreed language or reading level is not a saving.
07 How does the charter pay for NGO coordination, which cannot be priced per item in advance?Documented, pre-approved reimbursable expenses capped at USD 600. A fixed price agreed before requirements are confirmed. A percentage of the total project cost. An advance payment with no supporting records.
08 How does the guide classify an advance payment?As a contract type, alongside fixed price and reimbursable. As a form of contingency release. As a payment-timing decision that needs a business reason and sponsor approval. As a supplier incentive.
09 What does the charter say about allocating risk to a supplier or carrier?It removes the project's exposure to that risk. It ends the manager's duty to monitor that supplier. It transfers the risk to the sponsor. It does not remove the manager's duty to monitor performance or the project's exposure to disruption.
10 Which forecast level triggers a contingency review under R2?USD 6,000 USD 8,000 USD 9,200 USD 9,400
11 Why is customs clearance not one of the top three risks?Because international shipment is excluded from the scope, so books are sourced inside the country. Because the NGO handles it. Because customs risk is always low. Because the sponsor accepted that risk.
12 What does the charter say about arbitration and litigation?It imposes arbitration before any litigation. It leaves those arrangements to the actual contracts with appropriate local advice, and claims no enforceability. It rules both of them out. It requires litigation in the sponsor's jurisdiction.