Project Management · Module 4 · Applied case practice

Decide inside the limits you proposed.

These activities use a proposed, unsigned academic charter and its companion guide. They practise contracting judgment; they are not legal or financial advice, and they do not replace an organization's own procurement rules.

Decide as the project manager

The forecast reaches USD 8,400

Week 2. The best conforming book quotation is higher than assumed, and the manager's forecast for the whole project moves from USD 8,000 to USD 8,400. The ceiling is USD 9,200.

What does the charter require?

Knowledge check

Read the charter the way a sponsor would.

Choose the strongest answer from the charter, its companion guide and the Week 4 deck.

0/12 answered
01In version 2 of the charter, who may release contingency?
02The manager signs a USD 600 order with a supplier, then needs a second USD 600 order from the same supplier. What does the charter require?
03Why did delivery and handover move to the end of Week 5 in version 2?
04A quotation lifts the forecast total to USD 8,400 against a USD 9,200 ceiling. What does the guide say happens?
05What role does the charter give the NGO in the contracting structure?
06Why does the charter evaluate more than price when selecting a supplier?
07How does the charter pay for NGO coordination, which cannot be priced per item in advance?
08How does the guide classify an advance payment?
09What does the charter say about allocating risk to a supplier or carrier?
10Which forecast level triggers a contingency review under R2?
11Why is customs clearance not one of the top three risks?
12What does the charter say about arbitration and litigation?