01 A company borrows from a bank to build a factory it will use. According to the deck, who is the owner?The bank, because it provides the money. The company, because it executes the project with the borrowed funds and will take possession of the factory. The general contractor, because it builds the factory. The owner’s representative, because it oversees execution.
02 Why does the deck say owners must clearly define expectations and monitor contractors’ performance?Because contractors own the final outcome. Because contractors are always involved in every phase. Because contractors fund the project. Because contractors are profit-driven and have different priorities from the owner.
03 What does the deck call a long-lead item, and what should the owner do about it?Goods that take more than a year to manufacture or deliver; involve their suppliers early, during design and engineering. Any item costing more than the contingency; buy it last. Items supplied by the owner’s representative; approve them at closure. Materials bought under a purchase order; sign them bilaterally.
04 Which statement about the owner’s representative is correct?It replaces the owner during execution. It is a lender with oversight rights. It protects the owner’s interests, but final decisions and responsibilities remain with the owner. It executes the construction work.
05 Which list gives the five dimensions of contracting in the deck?Scope, schedule, cost, quality, and risk. Structure, payment, selection, risk, and dispute resolution. Owner, contractor, financier, supplier, and consultant. Negotiation, mediation, arbitration, litigation, and expert determination.
06 According to the deck, choosing between a single entity and a multi-prime model directly affects what?Project risk, coordination effort, and accountability. Only the contract price. The governing law of the contract. Which PPP model applies.
07 How does the deck, quoting PMI, define project risk?Any event that has already delayed the project. A dispute that has reached arbitration. The difference between the fixed price and actual cost. An uncertain event or condition that, if it materializes, impacts at least one project objective.
08 What does the deck say happens when a fixed price contract is signed without a sufficiently detailed statement of work?The buyer’s risk disappears, because the price is fixed. The contract automatically becomes time and material. Claims and disputes over what is in and out of the contract raise the risk of cost overruns or delay. The seller shares its profit margin with the buyer.
09 Under the deck’s graduated fixed price example, what happens when the supplier delivers late?It is paid for more hours, but at a lower rate: $90 instead of $110 per hour. It is paid for fewer hours at a higher rate. The contract is terminated immediately. It receives an award of up to $50,000.
10 Why might a buyer add a not-to-exceed clause to a time and material contract?To fix the hourly rate. To limit the total amount the buyer is required to pay. To make the contract bilateral. To share cost savings with the seller.
11 Why does the deck say a cost plus fixed fee contract gives the seller no incentive to inflate costs?Because the seller receives no fee. Because the buyer pays a percentage of costs. Because the fee is fixed before work begins and does not vary with actual costs. Because the fee is decided by an award board after completion.
12 What does the deck say about cost plus percentage of cost contracts?They are the preferred contract for nonprofit work. They are a type of fixed price contract. They give the buyer the most cost certainty. They are not allowed for US federal acquisitions under the federal acquisition regulations, and are bad for buyers everywhere.
13 In traditional design-bid-build, what is the relationship between the general contractor and the architect/engineer?They communicate, but have no contract with each other; each contracts with the owner. The general contractor works under the architect/engineer’s contract. They form a joint venture. The architect/engineer hires the subcontractors.
14 What is a GMP, and who usually provides it?A general management plan, provided by the owner. A government monitoring procedure, provided by financiers. A guaranteed maximum price, usually provided by the CM at risk. A graduated milestone payment, provided by suppliers.
15 What does value for money mean in a PPP, according to the deck?Always choosing the cheapest bid. Keeping every risk in public hands. Paying the private partner a percentage of costs. Considering life-cycle costs, innovation, and risk transfer, not just the cheapest bid.
16 What distinguishes arbitration from mediation?Arbitration is informal; mediation is a court process. In arbitration a private tribunal delivers a binding decision, while a mediator has no power to impose one. Mediation is always binding; arbitration never is. They are the same process under different names.