01 What two results does the assignment brief ask for?The work breakdown structure and the budget. The critical path and the total project duration. The crash cost and the fast-tracking plan. The project float and the calendar finish date.
02 What is the critical path of the assignment network?A → B → C → D → F → G. A → B → C → E → F → G. F alone, because it is the longest activity. A → B → C → D → E → F → G.
03 What is the total project duration?21 days. 26 days. 23 days. 22 days.
04 Why is adding all seven durations, 26 days, wrong?Because one activity is counted twice. Because the durations are in hours. Because it treats D and E as sequential, when they overlap in one five-day window. Because G is not part of the project.
05 Why is F’s early start day 14 rather than day 13?F must wait for the later of its predecessors’ finishes, and D finishes at 14. F’s duration is added to E’s finish. The two finishes, 14 and 13, are averaged. F always starts one day after testing.
06 In the backward pass, why is C’s late finish 9?Because 9 is C’s early finish, which is always copied. Because C’s late finish is the smaller of its successors’ late starts, min(9, 10). Because C’s late finish is the larger of its successors’ late starts. Because C has no successors.
07 How much total float does E have?None. Four days. One day. Nine days.
08 E starts one day late and then takes one day longer than planned. What happens?Nothing, because E has one day of float. Only F is delayed, not the project. E becomes a milestone. E finishes at day 15 and the project finishes at day 23, unless time is recovered elsewhere.
09 Why can project float not be calculated for this assignment?Because the brief imposes no project completion date. Because there is more than one path. Because E has float. Because the network has no milestones.
10 Why may prototype development and testing run at the same time in this exercise?Because testing never depends on development in real projects. Because the deck says testing is always parallel. Because the brief lists only C as E’s predecessor, not D. Because both take the same time.
11 If E took 6 days instead of 4, everything else unchanged, what would happen?Nothing; E is not critical. The project would take 23 days and the route through E would become critical. The project would take 21 days. Both paths would stay at 22 days.
12 If D took 3 days instead of 5, what would the project duration be?19 days. 20 days. 22 days. 21 days.
13 What does “critical” mean in this assignment?The activity has an effect on the project finish date. The activity is the most technically difficult. The activity is the longest single task. The activity is the most important to the client.
14 Which of these is an assumption the author made, rather than something the brief gives?That F depends on D and E. That every link is finish to start, with no leads or lags. That B takes 4 days. That A has no predecessor.