Project Management · Module 6 · Applied case practice

Run the network forward and back.

These activities use an academic critical path submission and its study guide. They practise reading dependencies, float and the effect of changes; they do not replace a real project’s calendar, resources or scheduling tools.

Decide as the scheduler

The teammate who adds everything

A teammate adds the seven durations in the activity table and reports a project duration of 26 days.

What is the best response?

Knowledge check

Check the calculation the way an assessor would.

Choose the strongest answer from the submission, its study guide and the Week 6 deck.

0/14 answered
01What two results does the assignment brief ask for?
02What is the critical path of the assignment network?
03What is the total project duration?
04Why is adding all seven durations, 26 days, wrong?
05Why is F’s early start day 14 rather than day 13?
06In the backward pass, why is C’s late finish 9?
07How much total float does E have?
08E starts one day late and then takes one day longer than planned. What happens?
09Why can project float not be calculated for this assignment?
10Why may prototype development and testing run at the same time in this exercise?
11If E took 6 days instead of 4, everything else unchanged, what would happen?
12If D took 3 days instead of 5, what would the project duration be?
13What does “critical” mean in this assignment?
14Which of these is an assumption the author made, rather than something the brief gives?