01 Which of these does the schedule management plan define?The project’s critical path. The individual duration of every activity. Measures of variance and the thresholds that trigger corrective action. The names of the work package owners.
02 What is the order of the deck’s five-step scheduling process?Defining, sequencing, estimating, scheduling, controlling. Estimating, defining, scheduling, sequencing, controlling. Scheduling, defining, estimating, controlling, sequencing. Defining, estimating, controlling, sequencing, scheduling.
03 How does the deck distinguish planning from scheduling?They are the same task under two names. Planning sets the ways, means, and steps; scheduling shows those steps on a calendar. Scheduling comes first and planning follows. Planning is for costs and scheduling is for scope.
04 As a ballpark, how much work should a work package take?One day at most. About a month. However long its owner decides. No more than two weeks, or 80 working hours.
05 Which is one of the deck’s guidelines for developing a WBS?Build it bottom up from individual tasks. Do not exceed about five levels. Leave work package owners until execution. Develop it independently of the charter.
06 What is true of a milestone?It is a significant event with no duration. It is the longest activity in the schedule. It is a work package owned by the sponsor. It is a lag between two activities.
07 In an activity-on-arc diagram, what represents the activities?The nodes. The parallelograms. The arcs. The milestones.
08 Wiring cannot start unless tubing has started. Which relationship is this?Finish to start. Finish to finish. A lag. Start to start.
09 Why are discretionary dependencies important when compressing a schedule?They are required by contract. They are the organization’s preferred sequence and can be changed, for example to fast track. They have no duration. They are set by the government.
10 A jurisdiction requires concrete testing before pouring. What kind of dependency is this?External. Internal. Discretionary and internal. A lead.
11 What is a lag?Starting an activity before its predecessor finishes. An activity on the critical path. Waiting time inserted between activities. A delay caused by negative float.
12 An activity has two activities directly preceding it. What is this called?Path divergence. Path convergence. Fast tracking. Rolling wave planning.
13 Which statement describes analogous estimation?It starts from detailed work package estimates. It needs story points. It is always more accurate than bottom-up estimation. It estimates the overall duration from similar past projects, roughly and early.
14 What is essential for bottom-up estimation to work?An accurate work breakdown structure. A project sponsor’s experience. A learning curve. A fast-tracked schedule.
15 What is the schedule baseline?The first draft of the network diagram. The critical activity list. The approved schedule, changed only through change management. The schedule management plan.
16 How much float do activities on the critical path have?As much as the project float. Zero. At least one day. Equal to their duration.
17 Which formula gives free float?Late start − early start. Late finish − early finish. Duration − total float. Early start of the next activity − early finish of the current activity.
18 In the forward pass, what is an activity’s early start?The largest early finish among its predecessors. The smallest late start among its successors. Its late finish minus its duration. Always day zero.
19 In the deck’s worked example, how long does the project take, and what is its critical path?25 days; D, F, G, H, C. 26 days; A, F, B. 26 days; D, E, G, H, C. 19 days; D, E, G, H.
20 What separates crashing from fast tracking?Crashing overlaps activities; fast tracking adds resources. Crashing adds resources and always adds cost; fast tracking overlaps critical activities and adds risk. Both reduce scope. Fast tracking changes the baseline; crashing does not.
21 In the deck’s crashing example, which activities should be crashed to recover three months, and at what cost?M alone, for 9,000 dollars. L and N, for 7,000 dollars. K, N, and L, for 17,000 dollars. J and N, for 5,000 dollars.