Project Management · Module 6 practice

Find the path that decides the date.

These guided activities are based on the supplied Week 6 source deck. They help you practise judgment about breakdowns, dependencies, estimates, float, and compression; they do not replace professional judgment or an organization’s own scheduling procedures.

Apply the module

The date that cannot be met

Management has announced a completion date. When you run the critical path on the agreed network, the project shows minus six weeks of float before any work has started.

What does the negative float tell you?

Knowledge check

Recall how a schedule is built, analysed, and compressed.

Choose the strongest answer from the supplied Week 6 material.

0/21 answered
01Which of these does the schedule management plan define?
02What is the order of the deck’s five-step scheduling process?
03How does the deck distinguish planning from scheduling?
04As a ballpark, how much work should a work package take?
05Which is one of the deck’s guidelines for developing a WBS?
06What is true of a milestone?
07In an activity-on-arc diagram, what represents the activities?
08Wiring cannot start unless tubing has started. Which relationship is this?
09Why are discretionary dependencies important when compressing a schedule?
10A jurisdiction requires concrete testing before pouring. What kind of dependency is this?
11What is a lag?
12An activity has two activities directly preceding it. What is this called?
13Which statement describes analogous estimation?
14What is essential for bottom-up estimation to work?
15What is the schedule baseline?
16How much float do activities on the critical path have?
17Which formula gives free float?
18In the forward pass, what is an activity’s early start?
19In the deck’s worked example, how long does the project take, and what is its critical path?
20What separates crashing from fast tracking?
21In the deck’s crashing example, which activities should be crashed to recover three months, and at what cost?