Decide as the estimator
The school wants ten beds After seeing the estimate, the head teacher asks whether the garden could have ten raised beds instead of four, in the same 8 m by 5 m plot.
What does the case’s approach suggest?
A Multiply the whole total by 2.5.B Revisit the scope first: check the beds fit, then recompute B’s kits, liners, fixings, soil and labour, and its overhead.C Keep the estimate; beds are a small part of the cost.D Move the extra beds into contingency.
Knowledge check
Check the estimate the way an assessor would. Choose the strongest answer from the submission, its study guide and the Week 7 deck.
0/12 answered 01 Which two figures does the brief itself specify?The garden’s size and the bench price. Labour at £100 per worker-day, and overhead of 10% to 15% of materials plus labour. The 12% overhead and the 10% contingency. The 17 worker-days and the £2,150 of materials.
02 What is the cost sheet’s grand total?£4,312.00. £3,850.00. £4,743.20. £4,379.20.
03 Which estimating method does the submission use?Top-down analogous, from a similar garden. A parametric cost per square metre. A class 1 check estimate. Bottom up: each activity estimated separately, then added.
04 How is the 25 m of fencing derived?From a supplier’s minimum order. From 8 m × 5 m = 40 m², rounded down. The perimeter 2 × (8 + 5) = 26 m, less a 1 m gate. From the four beds’ combined edges.
05 Why is all the soil priced in B rather than E?So that the same soil is not paid for twice. Because E has no budget. Because soil is an indirect cost. Because the school provides the soil.
06 What Week 7 term describes the submission’s list of items, quantities and rates?A quotation. A material takeoff. A cost management plan. A control account.
07 What do the 17 worker-days represent?The project lasts 17 calendar days. 17 workers on site for one day. The supervisor’s total time. £1,700 of paid effort, not the project’s calendar duration.
08 Why is the supervisor’s £300 in labour rather than in the overhead column?Because overhead cannot exceed 15%. Because the supervisor is a volunteer. Because Week 7 treats project manager pay as a direct cost; overhead covers only shared support. Because F has no materials.
09 What is the overhead on activity B?£139.20: 12% of £760 + £400. £91.20: 12% of materials only. £48.00: 12% of labour only. £155.90: 12% of B’s total.
10 Direct costs rise by £100. How much does the total rise?£100. £112. £88. £125.44.
11 How is the 10% contingency treated?Added inside the overhead column. Required by the brief and included in £4,312. Replacing the 12% overhead. Proposed separately, outside the table: £431.20, for £4,743.20 if accepted.
12 In the guide’s example, timber costs £60 more. What is left of a £431.20 reserve that covers it?£371.20. £431.20. £364.00. £359.20.
Check my answers