Project Management · Module 7 · Applied case practice

Price it, check it, control it.

These activities use an academic cost sheet submission and its explanation guide. They practise building, checking and controlling an estimate; they do not replace real quotations, an organization’s cost procedures or professional judgment.

Decide as the estimator

The school wants ten beds

After seeing the estimate, the head teacher asks whether the garden could have ten raised beds instead of four, in the same 8 m by 5 m plot.

What does the case’s approach suggest?

Knowledge check

Check the estimate the way an assessor would.

Choose the strongest answer from the submission, its study guide and the Week 7 deck.

0/12 answered
01Which two figures does the brief itself specify?
02What is the cost sheet’s grand total?
03Which estimating method does the submission use?
04How is the 25 m of fencing derived?
05Why is all the soil priced in B rather than E?
06What Week 7 term describes the submission’s list of items, quantities and rates?
07What do the 17 worker-days represent?
08Why is the supervisor’s £300 in labour rather than in the overhead column?
09What is the overhead on activity B?
10Direct costs rise by £100. How much does the total rise?
11How is the 10% contingency treated?
12In the guide’s example, timber costs £60 more. What is left of a £431.20 reserve that covers it?