01 Why does the deck insist on an accurate estimate before cost control?Because control is only needed on small projects. Because an unrealistic estimate is always impossible to control against. Because estimates replace the need for monitoring. Because lenders forbid changes to estimates.
02 Which of these is one of the three things to understand before estimating?The project’s critical path. The team’s personality types. How the project will be financed: the debt and equity mix. The AACE class of the final estimate.
03 Why do local content requirements matter to a cost estimate?They can require local sourcing and hiring, or ban some countries, limiting options for materials and labour. They only affect the project’s schedule. They apply to indirect costs only. They fix the exchange rate.
04 Which item belongs in a cost management plan?The activity durations. Control thresholds that trigger corrective action. The organigram. The project charter’s signatures.
05 Which cost does the deck warn estimators not to forget?The sponsor’s personal expenses. Costs of other projects. Sunk costs from earlier phases. Contingency and escalation.
06 How does the deck classify the project manager’s salary?Direct. Indirect. Fixed overhead. Escalation.
07 Which is an indirect cost?Concrete for the project’s slab. The project team’s travel. Head office costs. Wages of workers pouring the slab.
08 Which cost is variable?Site office rent. Tax on land rent. Setup costs. Concrete on a building project.
09 Can a cost be both direct and fixed?No, the categories exclude each other. Yes, the two ways of categorizing are not mutually exclusive. Only if it is also indirect. Only for equipment.
10 What characterizes bulk materials?Small, cheaper than equipment, and with labour costs nearly equal to material costs. Large and expensive, with minimal installation labour. Always imported. Always indirect costs.
11 What is a material takeoff?A seller’s priced offer with a validity period. A list of materials, with quantities and types, required to build a structure. A discount for buying in bulk. The removal of unused materials from site.
12 According to the deck’s best practices, how should significant items such as equipment be priced?With factors from past projects. With the sponsor’s target cost. With firm vendor quotes. With the lowest price found online.
13 Which is a disadvantage of top-down analogous estimation?It requires every activity to be identified. It is slow and expensive. It gains too much buy-in from the team. It does not consider differences between projects.
14 What risk does the deck attach to bottom-up estimation?The team may pad estimates unless it understands the use of reserves. It cannot be used for control. It is less accurate than top down. It never involves the team.
15 Which AACE class typically forms the basis for budget authorization and the initial control estimate?Class 5. Class 4. Class 3. Class 1.
16 A team only needs to assess a project’s feasibility. Which estimate does the deck say is sufficient?Class 1 only. Class 5 or class 4. Class 2 only. No estimate at all.
17 What does earned value (EV) measure?The money actually spent. The budget for the work scheduled to date. The total budget for the project. The budgeted amount for the work actually completed.
18 A project has EV of 80,000 and AC of 100,000 dollars. What is the cost variance?+20,000 dollars, under budget. −20,000 dollars, over budget. 0.8, over budget. 1.25, under budget.
19 BAC is 10,000 dollars and the CPI is 0.8. What is the estimate at completion?8,000 dollars. 10,800 dollars. 12,500 dollars. 2,000 dollars.
20 How does the deck build the cost baseline?Spread each activity’s cost evenly over its duration, add the daily costs, and accumulate them into an S-curve. Put each activity’s full cost on its start date. Divide the total budget equally across the months. Copy the baseline from a similar project.
21 In the country park example at month 17, what are the SPI and CPI?SPI 1.58, CPI 1.17. SPI 0.86, CPI 0.63. SPI 0.74, CPI 0.67. SPI 0.63, CPI 0.86.