Planning & Controls · probabilistic schedule analysis practice
Explain the estimate, then explain the confidence. Fourteen questions and four teaching scenarios cover the source's data, PERT arithmetic, network dependence, simulation inputs and percentile decisions. Each answer includes reasoning and a source slide reference. These are study questions created from the deck.
01 A path probability becomes a project promise02 A shared supplier affects several tasks03 An illustrative curve becomes an actual forecast04 A small record becomes a performance judgment
Decide what you would do
A path probability becomes a project promise A manager reads 97.4% next to A–B–D and tells the client that the complete project has that chance of finishing by day twenty.
Which response best preserves the analysis?
A Accept the promise because A–B–D is initially critical.B Multiply 97.4% by 90.4% to obtain an exact project probability.C Explain that the number describes one fixed path and review the full network, including the uncertain C branch and shared activities, before making a project-confidence statement.D Delete C because it is initially noncritical.
Knowledge check
Check what stuck. Choose the strongest answer from the supplied probabilistic schedule analysis material.
0/14 answered 01 For 3, 4, 4, 5 and 14 days, which set is correct?Mean 6, median 4 and mode 4. Mean 4, median 6 and mode 14. Mean, median and mode all equal 6. The 14-day value must be discarded.
02 What does Rami's larger sample standard deviation establish by itself?Rami is less capable. The recorded durations have greater variability. Every future duration is longer. The durations are normally distributed.
03 The first duration mentioned keeps influencing later estimates. Which bias fits?Availability. Positive skew. Anchoring. Monte Carlo sampling.
04 Under the deck's normal model, mean 10 and SD 2 days, the approximate central 95% interval is?8–12 days. 10–12 days. 4–16 days. 6–14 days.
05 What limitation does the deck state about the central limit theorem?It does not make every project finish normally distributed. It guarantees every activity's mean. It removes the need for a network. It establishes equal likelihood inside every duration range.
06 What is the expected duration for a=8, m=10 and b=16 days?10 days. About 10.67 days. About 1.33 days. 34 days.
07 Which unit belongs to the activity's estimated variance?Percent. Days. Days squared. Activities per day.
08 In the four-activity network, when can D start?Immediately after A. After whichever of B and C finishes first. At B's start. Only after both B and C finish.
09 Which path is critical using the expected durations?A–B–D, at 16.5 days. A–C–D, at 16.5 days. B–C–D, at 21 days. Both paths always tie.
10 What does the approximately 97.4% by day 20 calculation describe?A guarantee for the project. A–B–D alone under a normal approximation. The product of the two path probabilities. The percentage of project work complete.
11 Why must the two path deadline probabilities not be multiplied?Their durations have no units. D is not part of the project. The paths share A and D, connecting their risks. Each path is guaranteed to finish.
12 What should a simulation record across many complete-network trials?Only the original critical path at its mean. One fixed activity duration for every trial. Only the number of activities. Finish dates and which activities become critical.
13 Which input model assigns equal likelihood to equal-sized intervals within its range?Uniform. Triangular. Every beta-PERT model. Every normal model.
14 What does the illustrative P80 at 32.5 days mean?The work is eighty percent complete then. Eighty percent of modeled outcomes finish by that date. The project is guaranteed to finish then. The four-activity network has been simulated and must take 32.5 days.
Check my answers