01 Which three characteristics define a project in the supplied deck?Temporary, unique and progressively defined Permanent, repetitive and fully fixed Unbudgeted, informal and open-ended Routine, continuous and identical
02 Which set gives the deck's four life-cycle phases?Requirements, cost, risk and quality Concept, Planning, Execution and Closeout Charter, WBS, RTM and dictionary Approve, reject, update and repeat
03 A project finishes within budget but the client cannot accept its result. What follows from the deck?It is fully successful because cost is the only measure Client acceptance is irrelevant once execution ends The project is not fully successful The scope baseline has automatically changed
04 What turns monitoring into control?Adding more charts without decisions Waiting until the project closes Removing the approved reference Analyzing a deviation and taking corrective action
05 How should the Project Management Plan become the roadmap for work?Through collaborative development and formal approval Through the scheduler's private draft alone By replacing the scope definition Only after all work is complete
06 Which document establishes the project manager's authority and authorizes the project?WBS Dictionary Project Charter Requirements Traceability Matrix Quality-control report
07 Which sequence matches the supplied scope-management process?Create WBS, approve every change, then collect needs Verify delivery before defining the work Collect requirements, define scope, create WBS, verify scope, control scope Execute, close, collect requirements, then authorize
08 Which fields appear in the deck's RTM?Only activity dates and float Only cost and earned value Only an approver's signature ID, requirement, source, status and owner
09 What does the WBS 100% rule mean in this deck?Include all agreed work and no extra work Every activity must be completed on day one Every worker must be occupied every hour Include every requested addition automatically
10 Which combination forms the scope baseline?Charter, schedule and risk register Scope Statement, WBS and WBS Dictionary RTM, invoice and status report Quality checklist, Gantt chart and budget only
11 Which question is the deck's quality-control check?Were exactly 1,000 packages delivered? Were the identified families reached? Were packages fresh, sealed and nutritionally compliant? Did the sponsor formally accept completeness?
12 What is the proper response to a proposed scope change?Start the extra work and assess it after delivery Update the baseline before a decision Reject every request without review Assess impact, approve or reject, and reflect approved changes in affected baselines