01 In Exercise 2's AOA network, what do the numbered nodes represent?Events marking points in time. Activities with their own durations. Calendar dates. Resource quantities.
02 A two-day activity starts on the morning of day 1. When does it finish on Exercise 2's inclusive scale?Beginning of day 1. End of day 2. End of day 3. Beginning of day 4.
03 Several incoming relationships give different lower bounds on an activity's start. Which value does the forward pass use?The smallest bound. Their average. The largest bound. The first condition listed.
04 Which pair controls the twenty-week result in Exercise 1?A–I–M and C–F–K–N. A–D–H–M and A–I–M. B–E–J–M alone. B–E–J–M and C–G–L–N.
05 Starting from the original Exercise 1 schedule, what happens if H's duration increases by two weeks?Completion becomes 21 weeks, one week late. Completion stays 20 weeks. Completion becomes 22 weeks. N finishes earlier and cancels the delay.
06 How should the fifteen-day Exercise 2 result be displayed?Completion at the end of day 16. Completion at the end of day 15. Completion at the start of day 15 after fourteen elapsed days. A sixteen-day duration because the labels start at one.
07 H in Exercise 2 has total float 5 and free float 4. What is its interfering float?9 days. 4 days. 1 day. 0 days.
08 Why is G's independent float zero even though its free float is six days in Exercise 2?Float is never defined for AOA. G is a critical activity. The duration must be increased by six. A late event 4 at time 7 uses the interval before event 6 at time 10.
09 What controls B's earliest start at 3 in Exercise 3?SS +3 from A is stronger than the FF +4 start bound of zero. B must wait for A to finish at 8. Only the FF +4 relationship applies. The two relationships are averaged.
10 D starts at 15 and D-to-F is SF +12. F lasts 12 units. What finish does that condition require?F finishes at 21 because D finishes then. F finishes no earlier than 27. F starts no earlier than 27. F finishes exactly when C finishes at 13.
11 D runs from 7 to 17. J lasts 6 and has SS +3 and FF +2 after D. What is J's earliest start?10. 19. 13. 7.
12 Why can K start at 5 before H starts at 9 in Exercise 4?All dependencies may be ignored if work overlaps. H-to-K is finish-to-start. K has a negative duration. SF +3 restricts K's finish at 12 using H's start at 9.
13 Why does the Exercise 5 controlling sequence take 45 days rather than the 50-day sum of its activity durations?H overlaps E's final five days through their FF 0 relationship. A's duration is omitted from the model. Five days of total float are subtracted from every critical activity. D and E have no relationship.
14 Which set matches F in Exercise 5?TF 5, free 5, interfering 0, independent 5. TF 5, free 0, interfering 5, independent 0. TF 0, free 5, interfering 5, independent 0. TF 10, free 5, interfering 5, independent 5.
15 Which statement correctly interprets the guide's X–Y–Z extension?Ken has an 84.13% on-time probability and a guaranteed $4,730.76 profit. Each of the five assignment networks has standard deviation 3. Its invented inputs give mean 20, standard deviation 3, approximate probability 84.13% by day 23 and EMV $4,730.76. Its three standard deviations are added to obtain the path standard deviation.