01 What does progressive elaboration mean in the recording?The project repeats routine operations. The project details become clearer as information develops. Every request is accepted without review. The project has no defined ending.
02 The project is on time and within budget, but its result fails the client's required needs. What does the session conclude?The project is automatically fully successful. Client acceptance can be ignored after delivery. The project is not fully successful merely because its delivery targets were met. Only the size of the team matters.
03 Which action is monitoring?Measuring actual progress and comparing it with the plan. Approving a revised scope baseline. Assigning corrective action after analyzing a deviation. Choosing to change resource priorities.
04 Who develops the project management plan in the lecture's account?The client alone, without the delivery team. A software tool independently. The project manager alone, without other input. The project manager with input from the team and key stakeholders.
05 Which pairing matches the recording?Charter: detailed work packages; Scope Statement: activity dates only. Charter: authorization; Scope Statement: detailed boundaries; management plan: delivery and control. Charter: food quality inspection; management plan: formal project ending only. All three documents have identical roles.
06 What information does the session name for a requirements traceability matrix?Only the project's total budget. Only the final completion percentage. Requirement identity and description, source, status and owner. The names of every scheduling product.
07 What does the WBS 100% rule mean here?Represent all agreed work without adding unapproved extra work. Every work package is already complete. Every project must contain exactly 100 activities. A small requirement may be omitted if it is easy.
08 Which three elements make up the scope baseline in the recording?Charter, attendance list and quiz score. Risk log, final invoice and handover date. Only a schedule, budget and client email. Scope Statement, approved WBS and WBS dictionary.
09 In the NGO example, checking freshness and proper sealing is primarily which check?Project authorization. Quality control. Counting WBS branches. Selecting scheduling software.
10 A stakeholder proposes extra work. What sequence follows the session?Start immediately, then ask about the cost. Rewrite the baseline before discussing the request. Request, assess impact, approve or reject, then update baselines as required for approved changes. Refuse every request because a baseline exists.
11 What hybrid approach is discussed when an Agile project has an overall client deadline?Plan the overall deadline, budget or milestones while using Agile for detailed delivery. Guarantee all future scope without reviewing changes. Remove all milestones and client commitments. Require every industry to use the same software.
12 What principle supports the lecturer's AI diagramming example?A polished diagram proves all work is correct. The learner no longer needs to read the scope. AI output should be accepted without correction. The learner supplies the thinking and reviews and corrects the generated representation.