Planning & Controls · 5 November recording practice

Explain the model, then defend the scheduling decision.

Fourteen knowledge-check questions and five teaching scenarios cover work definition, dependencies, durations, paths, float, baseline control and compression. They apply the recording's concepts and include explanatory feedback; they are not official assessment questions.

Decide what you would do

A tidy file with hidden work

A team has a complete-looking Gantt chart, but several activities are disconnected and curing is represented only by an unexplained lag. The sponsor asks whether the finish date is dependable.

What is the best next step?

Knowledge check

Check what stuck.

Choose the strongest answer from the supplied 5 November recording material.

0/14 answered
01Which sequence follows the session's executable-schedule process?
02Why is complete first review clearer than reviewing?
03The lecturer prefers finishing all slides before rehearsal, but could rehearse a draft. What kind of logic is that?
04Why does the session recommend showing concrete curing as an activity?
05What event relationship represents the outgoing shift staying until the incoming shift begins?
06Teaching check: Q=240 units, P=20 units per crew-day and N=2 effective crews. What duration does the formula give?
07How should the lecturer's 75% and 90% availability figures be used?
08The three dependent paths take fourteen, twelve and eleven days. Which result matches the recording?
09Which timing measure specifically protects a successor's early start?
10What does negative float indicate in this session?
11An unchanged-scope deliverable is late. Which response preserves useful control?
12What trade-off does the late-start S-curve illustrate?
13Which proposal is fast tracking?
14Two separate critical paths are twenty days each. One is crashed to eighteen. What is the project duration if the other is unchanged?