01 For the recording’s durations 3, 4, 4, 5 and 14 days, which statement is correct?Mean 6, median 4 and mode 4. Mean, median and mode all equal 6. Mean 4, median 6 and mode 14. The longest value must be removed before any calculation.
02 One recorded set has a much larger standard deviation than another. What can you conclude from that fact alone?Its worker is less capable. It shows greater duration variability in those records. It has a normal distribution. Its future activities must always take longer.
03 A first estimate dominates later discussion even after relevant records are reviewed. Which bias best matches?Availability. A uniform distribution. Anchoring. A backward pass.
04 Under the source’s normal model with mean 10 and standard deviation 2 days, about 95% lie where?8 to 12 days. 4 to 16 days. Exactly at 10 days. 6 to 14 days.
05 What is the useful idea in the repeated fifty-roll dice explanation?Averages from many repeated batches can approach a bell-shaped pattern under suitable conditions. Every individual roll becomes normally distributed. Every batch average must equal 3.5 exactly. Every project finish must follow a normal model.
06 What is the PERT expected duration for a=8, m=10 and b=16 days?10 days. About 10.67 days. About 1.33 days. 34 days.
07 Which statement keeps the units and simple independent-path calculation correct?Variance is measured in days and standard deviations always add. Path variance equals the largest activity mean. Variance is measured in days squared; independent activity variances add before taking a square root for path standard deviation. Variance and expected duration are interchangeable.
08 Two routes contain the same activity. How should a Monte Carlo trial handle that activity?Draw independently for each route. Delete it from one route. Force it to its mean in every trial. Use one sampled duration consistently wherever it appears within that trial.
09 Why recalculate the full network in each simulation trial?The path controlling completion can change as durations change. A trial removes all predecessor restrictions. Every path must have the same finish. The deterministic critical path must always remain critical.
10 Which statement correctly clarifies the distribution-choice Q&A?Triangular and uniform both give every interval equal probability. Triangular has a mode; uniform gives equal likelihood to equal-sized intervals inside its bounds. The most likely estimate is always the arithmetic mean. Any tightly clustered data must be normal.
11 In the illustrative curve, P80 is 32.5 days. What does that mean?The project is eighty percent complete at 32.5 days. Every activity lasts 32.5 days. Eighty percent of modeled whole-project outcomes finish by 32.5 days and twenty percent later. Completion at 32.5 days is guaranteed.
12 In a simple FS+0 network, a successor has predecessor early finishes of 6 and 9. With no other restrictions, its early start is?6, because the first predecessor has finished. 7.5, the average of the finishes. 15, their sum. 9, because both predecessors must be finished.
13 A starts at time 0 and its successor has an SS+5 link. What does that link require?The successor starts no earlier than time 5; another restriction may require a later start. A must finish before the successor starts. The successor must finish at time 5. The successor’s duration must equal five days.
14 Which example in the recording illustrates soft logic?Obtaining a blood sample before reporting its test result. Choosing whether to draft presentation slides or the script first. Excavating before dependent foundation work. Preserving a physical construction requirement.