Planning & Controls · 12 November session practice

Explain the uncertainty, then defend the decision.

Fourteen questions and four teaching scenarios test the session’s statistics, PERT arithmetic, model assumptions, percentile interpretation and network reasoning. Use the feedback to revisit the source discussion and distinguish its examples from the guide’s mathematical clarifications.

Decide what you would do

A date without its probability

A manager selects the recording’s illustrative thirty-day date for a client promise and says the simulation proves the team will finish on time.

What is the most useful response?

Knowledge check

Check what stuck.

Choose the strongest answer from the supplied 12 November session material.

0/14 answered
01For the recording’s durations 3, 4, 4, 5 and 14 days, which statement is correct?
02One recorded set has a much larger standard deviation than another. What can you conclude from that fact alone?
03A first estimate dominates later discussion even after relevant records are reviewed. Which bias best matches?
04Under the source’s normal model with mean 10 and standard deviation 2 days, about 95% lie where?
05What is the useful idea in the repeated fifty-roll dice explanation?
06What is the PERT expected duration for a=8, m=10 and b=16 days?
07Which statement keeps the units and simple independent-path calculation correct?
08Two routes contain the same activity. How should a Monte Carlo trial handle that activity?
09Why recalculate the full network in each simulation trial?
10Which statement correctly clarifies the distribution-choice Q&A?
11In the illustrative curve, P80 is 32.5 days. What does that mean?
12In a simple FS+0 network, a successor has predecessor early finishes of 6 and 9. With no other restrictions, its early start is?
13A starts at time 0 and its successor has an SS+5 link. What does that link require?
14Which example in the recording illustrates soft logic?