Planning & Controls · 19 November session practice

Explain the load, then defend the resource decision.

Fourteen questions and five teaching scenarios test allocation, responsibility, time-phased capacity, priority, smoothing, leveling and the finance/cost/AI discussion. Use the feedback to separate spoken examples from the guide’s added calculations and clarifications.

Decide what you would do

The capacity total looks comfortable

A manager sees 101 worker-weeks of work and 108 worker-weeks of availability and promises the twelve-week finish. The resource profile shows fourteen workers needed in Week 5, with only nine available.

What is the best next step?

Knowledge check

Check what stuck.

Choose the strongest answer from the supplied 19 November session material.

0/14 answered
01The same engineer has six hours of drawing review and four hours of inspection on Monday. What is resource loading in this example?
02Which check fits the session’s fixed stock of one hundred steel beams?
03Why does the generator example need two resource checks?
04What connects work items in the WBS with people and teams in the OBS?
05Why does 108 available worker-weeks not prove the 101-worker-week project can finish in twelve weeks?
06Two ready activities need the same machine. One has zero total float and the other three days. Which priority follows the lecture’s usual rule?
07C needs five compressors and D needs two, with six available. What is the concurrent conflict?
08What can this recording alone establish about the proposed D placement?
09Which proposal best fits resource smoothing?
10Which statement about leveling is the most careful reading of the session?
11What must be true for moving Monday’s report work to the preceding Wednesday to be feasible?
12Which cost conclusion follows the Q&A?
13How should the three-days-to-one-day AI example affect an estimate?
14Which resource consideration does the closing AI discussion add explicitly?