Planning & Controls · Week 5 practice
Explain the protection, then test the resource plan.
Twelve questions and four hypothetical scenarios check the delay mechanisms, buffer roles, constraint focus and portfolio decisions. Feedback points back to the supplied summary’s document paragraphs.
Decide what you would do
Two reviews and one specialist
Two reviews have no logical dependency between them and are both ready. Each requires the full attention of the same available specialist.
What should the schedule discussion recognize?
Knowledge check
Check what stuck.
Choose the strongest answer from the supplied Week 5 material.