Original source guide
Week 1: The Front End
This map preserves the deck’s teaching sequence while the lessons provide a clearer, client-facing explanation. Use it to trace every study topic back to the supplied source.
How to use this pageOpen a lesson source note for its original teaching focus and slide range. The deck itself is not republished here; distribute the original PDF only when you hold the necessary rights.
Lesson 01
From an idea to an authorized project
See where projects begin and why the most important choices happen before execution.
Open learner explanation →Original project-phase framingThe source presents pre-project/front-end loading, execution, and closeout/operations, and contrasts industrial terminology with needs assessment and project design in humanitarian work.
Source slides 2-15 Original sponsor and business framingThe source identifies the sponsor as champion and advocate, and the business as the beneficiary that defines the need, funds it, and uses the outcome.
Source slides 16-18 and 24-28 Lesson 02
Assess, select, and define
Follow the three front-end subphases that turn an idea into a decision-ready proposal.
Open learner explanation →Original three-subphase modelThe source names Project Assessment, Concept Selection, and Project Definition, and stresses that their depth varies with project size and complexity.
Source slides 20-23 Original charter and pre-project planning contentThe source covers the project charter, the pre-project plan across sectors, parallel definition work, risk analysis, execution management planning, and the authorization package.
Source slides 29-39 Lesson 03
Feasibility and alternatives
Test whether a project can and should work before treating its first idea as the answer.
Open learner explanation →Original feasibility areasThe source lists technological, legal, operational, and market feasibility, supported by examples such as a solar project.
Source slides 41-42 Original alternative-evaluation flowThe source diagram moves through technology and location analysis, conceptual scope, conceptual estimates, and comparison of alternatives.
Source slides 43-44 Lesson 04
Value and project selection
Use appropriate economic or value-for-money measures to compare a project’s expected contribution.
Open learner explanation →Original economic-selection contentThe source introduces time value of money, present value, NPV, payback period, benefit-cost ratio, and IRR, including their intended use and limitations.
Source slides 45-55 Original humanitarian value contentThe source explains why direct-revenue metrics often do not fit humanitarian work and presents value-for-money, cost-effectiveness, cost-benefit analysis, and social return on investment examples.
Source slides 56-60 Lesson 05
Stage gates and the cost of late change
Use evidence-based review points to continue, revise, pause, or stop before the cost of change rises.
Open learner explanation →Original gated-process contentThe source explains why gates occur between assess, select, and define; identifies cancel, return for information, and proceed decisions; and describes early project termination as healthy when justified.
Source slides 62-67 Original influence and sponsor contentThe source uses the cost influence curve to show falling influence and rising cost, then describes higher sponsor involvement during the early phases.
Source slides 68-81 Lesson 06
Governance and assurance
Clarify who sets direction, who makes decisions, and who independently checks the project’s health.
Open learner explanation →Original governance contentThe source defines governance and presents structure, processes, accountability, and oversight as its core elements, including the needed organizational inputs.
Source slides 83-90 Original review and assurance contentThe source explains individual and committee reviews, independent project assurance, and the difference between governance and assurance.
Source slides 91-98 Lesson 07
Scope that protects delivery
Define what the project will and will not deliver so the team can plan, control, and align expectations.
Open learner explanation →Original scope definition and examplesThe source defines scope, describes open scope and scope creep, and gives in-scope/out-of-scope examples for construction, humanitarian response, and a mobile banking application.
Source slides 100-111 Original scope-statement contentThe source identifies product features, project work, deliverables, acceptance criteria, exclusions, assumptions, and constraints as parts of a scope statement.
Source slides 112-114 and 119-120 Lesson 08
WBS, requirements, and controlled change
Turn scope into manageable deliverables, gather requirements, and resist unapproved extras.
Open learner explanation →Original WBS and best-practice contentThe source explains WBS as a hierarchical visual breakdown and notes that multiple valid structures can suit different organizations and project types.
Source slides 115-120 Original change and requirements contentThe source covers gold plating, context diagrams, mind maps, product analysis, project charter, scope-management plan, assumption log, risk register, and the project scope statement.
Source slides 121-129