Budget, milestones and assumptions

A transparent cost build-up with contingency inside the ceiling, six milestones counted from the day of signature, and the assumptions that could still undo them.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

The cost build-up

The Week 2 cost logic is kept. Books at an average of USD 3 each come to USD 6,000. Adding USD 400 for packaging, USD 1,000 for domestic transport and USD 600 for coordination and inspection gives a base estimate of USD 8,000. Contingency of 15% of that base adds USD 1,200, so the maximum cash budget is USD 9,200. The allowances are planning assumptions, not market quotations or verified local prices.

Cost build-up · Charter §5
Cost componentPlanning basisUSD
Books2,000 books at USD 3 average6,000
PackagingProtective cartons and packing materials400
Domestic transportSupplier collection and school distribution1,000
Coordination and inspectionLocal operational support600
Base estimateSum of the four allowances8,000
Contingency15% of the USD 8,000 base1,200
Maximum cash budgetBase plus contingency9,200

Contingency sits inside the ceiling

The 15% applies to the base, not to the USD 9,200 total, and contingency must not be added twice. It is inside the ceiling: not extra funding, and not an allowance for extra scope.

  • Using it needs a recorded justification and the approvals set out in the charter's authority section.
  • It is not a spending target. Unused funds stay with the sponsor.
  • Supplier and transport quotations must include applicable charges before commitments are approved. Taxes and fees are not assumed to be zero.

Time given in-kind

A small coordination allowance would mislead if readers thought it covered six weeks of professional salaries. The charter therefore assumes that the sponsor, the Project Manager and the school representatives contribute time in-kind, recorded separately from the cash budget. The USD 600 allowance covers local operational support only.

Applied choiceThe in-kind assumption is the author's addition for this case. If essential participants need paid time or travel, the estimate must be revisited, and unpaid effort still has workload and availability limits.

Six weeks from authorization

The clock starts at signature. Week 1 begins on the authorization date and Week 6 ends 42 calendar days later, so no start date is invented. Purchasing happens only after requirements are agreed, and receipt is targeted for Week 5 so that Week 6 can absorb corrections. In the charter's words, Week 6 is “not spare capacity for additional deliverables”. Local stock and a single district make six weeks plausible, but not guaranteed.

A timeline of six weeks measured from the sponsor's signature, running from day 0 to day 42. Day 0 is the authorization gate: the sponsor signs, and funding and delegated authority are confirmed. Week 1 is marked protected: schools, book list, allocation and quotations are agreed, and purchasing is blocked until that agreement is done. Weeks 2 and 3: approved books are purchased, inspected and packed. Week 4: domestic transport and distribution. Week 5: school receipt, replacements and handover. Week 6 is marked protected: outstanding corrections and final acceptance, ending on day 42. A note at the foot says Week 6 is not spare capacity for extra deliverables.
Six weeks from authorization, with Week 1 and Week 6 protected · Charter §5, §6
Milestones and completion evidence · Charter §5
PeriodMilestone or completion evidence
AuthorizationSponsor signs; funding and delegated authority confirmed
Week 1Schools, book list, allocation and quotations confirmed
Weeks 2-3Approved books purchased, inspected and packed
Week 4Domestic transport and distribution undertaken
Week 5School receipt, replacements and handover completed where possible
Week 6Delay allowance, outstanding corrections and final acceptance completed

Assumption, constraint, dependency, risk

The guide gives one example of each term from this project. The distinction between the terms follows the deck; the examples are applications to the case.

Four terms, one project · Guide §5 · Deck pp. 9-12, 23-24, 31-39
TermExample in this project
AssumptionSuitable books will be available from in-country stock
ConstraintThe project must remain within USD 9,200
DependencySchool agreement must precede purchasing
RiskThe assumed stock or price may not be available when required

Fixed constraints and preconditions

The fixed planning constraints are 2,000 accepted books, four schools, six weeks and USD 9,200. Two conditions come before any commitment.

  • Funding availability is a precondition to authorization.
  • Week 1 confirmation of stock, quotations, school participation and delivery access is a prerequisite to purchasing.
  • If these assumptions fail, the Project Manager will seek a sponsor decision rather than silently reduce quantity, quality or coverage.

Study explanation of a proposed academic charter and its companion guide, read against the supplied Week 3: The Project Charter course deck. Open the source notes above to see which document each claim comes from.