Responsibility is not authority
Responsibility is the obligation to deliver. Authority is the right to decide and to commit resources within limits. A Project Manager can be responsible for the budget without being allowed to increase it. In this charter, the sponsor owns the charter, authorizes the overall budget and keeps the decisions that affect its fundamental commitments. The Project Manager coordinates delivery, keeps records, manages the approved resources and reports. The limits do not imply unrestricted authority over partner staff or funds.
The delegated limits
The charter sets out five decision areas, each with what the Project Manager may decide and what goes to the sponsor.
| Decision area | Delegated Project Manager authority | Sponsor approval or escalation |
|---|---|---|
| Purchasing | Approve orders up to USD 1,000 per procurement package within approved funds | Larger packages, including the estimated USD 6,000 book purchase; orders must not be split to avoid approval |
| Budget transfers | Reallocate up to USD 400 cumulatively between base-budget lines without changing objectives or the total | Transfers above that cumulative limit, and any proposed increase to the USD 9,200 ceiling |
| Contingency | Release up to USD 300 per risk event and USD 600 cumulatively, within the USD 1,200 reserve | Releases exceeding either limit; purchasing limits still apply |
| Schedule and scope | Resequence internal work by up to three working days per milestone, keeping Week 1 agreement and Week 6 completion; clarify work without changing deliverables | Larger shifts, or any change to quantity, quality, schools, exclusions or protected deadlines |
| Resources and communication | Assign tasks within agreed partner capacity, coordinate stakeholders and issue weekly reports; pause unsafe activity or reject nonconforming books | Extra paid capacity or uncommitted partner resources; major disputes and high-impact responses beyond delegated limits |
Applied choiceEvery limit in this table is the author's proposal for this small case, sized for a USD 9,200, six-week project. None of them is a course or industry threshold.
Why these numbers
The guide gives a reason for each limit. Together they allow routine local decisions while protecting the largest purchase and the overall commitments.
| Control | Why it was selected |
|---|---|
| USD 1,000 per procurement package | Allows routine local orders while reserving the main USD 6,000 book commitment for the sponsor |
| USD 400 cumulative transfers | Limited flexibility equal to 5% of the USD 8,000 base, without increasing total funds |
| USD 300 per event; USD 600 cumulative contingency | Small responses allowed; the sponsor keeps oversight of at least half the USD 1,200 reserve |
| Three working days per milestone, protected deadlines | Resequencing allowed, but no permission to miss Week 1 agreement or Week 6 completion |
| One working day to escalate; two requested for sponsor response | Clear expectations for urgent decisions, without treating silence as consent |
The deck's example, scaled down
The deck's example delegation table uses far larger amounts and allows a two-week schedule delay. The guide keeps the table's decision-and-escalation logic, not its example values, because copying the deck's figures would be disproportionate to a USD 9,200, six-week initiative.
| Deck example area | Deck example limit | Charter counterpart | Charter limit |
|---|---|---|---|
| Project budget adjustments | Up to USD 10,000 variation | Budget transfers | USD 400 cumulative between base lines; total unchanged |
| Scope changes | Minor, with no cost or time impact | Schedule and scope | Clarify work without changing deliverables |
| Schedule adjustments | Up to a 2-week delay | Schedule and scope | Up to 3 working days per milestone; Week 1 and Week 6 protected |
| Resource allocation | Functional managers, within department limits | Resources and communication | Within agreed partner capacity |
| Contractual commitments | Procurement lead, up to USD 50,000 | Purchasing | Up to USD 1,000 per package; no order splitting |
| Risk response actions | Low to medium risks | Contingency | USD 300 per event, USD 600 cumulative |
Read with careThe deck's page 64 figures are illustrations, and the charter's limits are the author's design choices; neither set is a benchmark. This comparison table is a study aid built for this module. The guide itself says only that the deck's amounts are much larger and that it allows two weeks for schedule.
Reporting, escalation and the decision log
Weekly sponsor reports will cover accepted quantities, milestones, spending, commitments, forecast completion and risks.
- Threats to charter objectives are escalated within one working day, and the sponsor is asked to respond within two working days.
- Silence does not constitute approval.
- Decisions, transfers and reserve use are logged, so repeated small changes cannot get around the cumulative limits.
- A change affecting the charter needs a written impact assessment and sponsor reauthorization, including a fresh look at feasibility.
- Routine changes to the detailed plan within these limits do not rewrite the charter.
Applied choiceThe one-day escalation window and the two-day response request are the author's choices for this case. They make urgent decisions predictable without treating silence as consent.
Three decision tests
The guide tests the limits against three situations.
- An extra USD 200 for a domestic reroute. The Project Manager may approve it only if it is an in-scope response, the per-event and cumulative contingency limits still have room, the purchasing limits are met, and the total forecast stays within USD 9,200. The decision must be logged. If the reroute takes the transport package above USD 1,000, sponsor approval is still required.
- A USD 600 price increase on the main book order. Sponsor approval is required, because the book package already exceeds the purchasing threshold and USD 600 exceeds the per-event contingency limit. Money available in the reserve does not by itself create authority.
- Adding a fifth school without more money. Sponsor approval is required, because the recipient boundary changes. No extra cost does not mean no scope change, and the allocation and beneficiary agreement would need review.
Why a RACI chart does not replace the table
A RACI chart says who is Responsible, Accountable, Consulted and Informed. A delegation of authority says what a role may decide and within which limits. Saying the Project Manager is responsible for purchasing coordination does not answer whether the Project Manager may approve a USD 6,000 order; the authority table does. The deck treats the two tools as complementary, and this charter does not include a detailed RACI.
Competence is not authority
The transferable lesson is a principle. Knowing the best approach does not let anyone change what the client receives without the right business decision. Equally, no one should be held responsible for an outcome without authority over the resources and decisions it needs.