Project Management · Module 3Lesson 8

Study explanation · Lesson 08 · 12 min

Responsibility, authority, and the RACI chart

Separate the obligation to deliver from the right to decide, and use a RACI chart alongside the delegation of authority to show who does what and who decides what.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

Responsibility is not authority

Responsibility is the obligation to complete a task or deliver an outcome, and everyone on a project team has some. Authority is the right to make decisions or allocate resources to fulfil those responsibilities. A team member may be responsible for delivering something while only the project manager has the authority to approve changes to its budget or timeline. Keeping the two clear means people are not held accountable for outcomes they were never empowered to control.

RACI and delegation work together

A RACI chart and the delegation of authority both clarify roles, decisions, and accountability, but they answer different questions.

  • A RACI chart maps who is Responsible for a task, who is Accountable for decisions, who must be Consulted, and who should be Informed.
  • The delegation of authority defines who has the authority to make decisions, and under what conditions.
  • Together they show not only who does what, but also who decides what.

A RACI template for a humanitarian project

The deck closes with a template RACI chart for a humanitarian project.

RACI template for a humanitarian project · Source slide 73
ActivityProject managerLogistics coordinatorField personnelFinance officer
Needs assessmentARRI
Procure relief suppliesRACI
Distribute aidARII
Prepare financial reportACCC
Finance officer, as labelledRCCA

Read with careAs shown in the deck, the last row is labelled with a role, Finance Officer, rather than an activity, and the prepare financial report row marks no one as Responsible. Check both before reusing the template.

Study explanation based on the supplied Week 3: The Project Charter source deck. Open the source notes above for slide-level traceability.