Project Management · Module 3Applied casePart 6

Applied case · Part 06 · 16 min

The top three risks

Three medium-likelihood, high-impact risks, each found by testing an assumption behind an objective, each with a monitor, a first response and a trigger for escalation.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

Framing the risks

These are the initial risks that most directly threaten timely delivery, affordability and beneficiary value. Likelihood and impact are qualitative planning judgements, not measured probabilities, and detailed assessment follows authorization. The charter records the main uncertainties and who monitors them, and leaves a full risk plan for later.

Read with careThe deck's page 35 slide says “Quantitative Impact Summary”, but its notes on page 36 and pages 42-43 describe a high, medium or low assessment without detailed statistics. The charter follows the notes and does not manufacture numeric probabilities.

Three risks at a glance

All three are rated medium likelihood and high impact. Two are external and one is internal.

The top three risks · Charter §7
RiskClassMonitorEscalation trigger
R1 · Domestic delivery disruptionExternalNGO logistics coordinatorForecast delivery or replacement beyond Week 6
R2 · Prices or delivery charges exceed allowancesExternalProject Manager, supported by financeForecast above USD 9,200 needs immediate sponsor review
R3 · Inadequate validation of school needs and readinessInternal: project engagement and requirements validationNGO education coordinatorMissing approvals block purchasing; unresolved suitability or access concerns block final acceptance

R1: domestic delivery disruption

If transport availability, road access or handling conditions differ from the assumptions, deliveries may arrive late, incomplete or damaged, preventing acceptance of 2,000 usable books within six weeks. It is prioritized because every school depends on physical delivery, even with in-country sourcing.

  • Monitor: the NGO logistics coordinator.
  • Initial response: validate access and receiving arrangements, confirm protective packing, and identify an alternative domestic carrier. Receipt is targeted for Week 5 so that Week 6 can absorb corrections.
  • Escalation: when forecast delivery or replacement goes beyond Week 6.

R2: prices or delivery charges exceed allowances

If book prices or transport charges exceed the assumptions, the cash ceiling may be breached or the full collection may become unaffordable. The USD 6,000 book allowance is most of the base estimate, so extra fees could consume the contingency.

  • Monitor: the Project Manager, supported by finance.
  • Initial response: obtain inclusive quotations, compare alternatives, and monitor the forecast before ordering. In-scope responses may use contingency within delegated limits.
  • Escalation: a forecast above USD 9,200 needs immediate sponsor review. Fewer books or lower quality are not acceptable unapproved savings.

R3: inadequate validation of school needs and readiness

If the team buys without meaningful school input or confirms handover too late, books may be unsuitable, allocations disputed or pupil access unavailable. The project could hit a transport target and still fail its intended value.

  • Monitor: the NGO education coordinator.
  • Initial response: obtain the Week 1 agreement, verify custodians and access, and involve teachers in acceptance.
  • Escalation: missing approvals block purchasing, and unresolved suitability or access concerns block final acceptance.

The assumption behind each risk

Each risk applies the deck's assumption-testing method: any assumption that proves false may be a significant risk. Reading the three together shows which objective each one protects.

Assumptions tested and objectives threatened · Guide §7 · Deck pp. 37-38
RiskAssumption testedObjective threatened
Domestic delivery disruptionRoad access, handling and carrier availability will support deliveryQuantity, quality and Week 6 completion
Prices or charges exceed allowancesThe assumed book and transport allowances will be sufficientThe USD 9,200 ceiling and full delivery
Inadequate validation of school needs and readinessRecipient agreement and access will be established before commitmentsSuitability, participation and useful handover

Against the deck's checklist

The deck lists what a charter risk entry typically records. This charter covers each element.

Study cross-walk: the deck's risk elements and this charter · Deck pp. 35-36 · Charter §7
The deck's elementIn this charter
High-level descriptionAn if-then statement for each risk
Internal or external classificationR1 and R2 external; R3 internal
Impact summary: high, medium or lowMedium likelihood and high impact, rated qualitatively
Assumptions and dependencies that may trigger itThe assumption each risk tests, and the charter's Section 4
Risk ownership, which is optionalA named monitor, by role, for each risk

Why R3 is internal

The first two risks are external because their triggers are carrier conditions and supplier charges. R3 is framed as internal because the specific failure is the team's own inadequate engagement and validation, which fits the deck's process category of internal risk.

Read with careCalling R3 internal does not claim that school behaviour is controllable. It classifies the team's own validation process, not the schools.

What was not copied, and how to validate

Customs delays from the brief's examples were left out, because international shipping is excluded; if the sourcing changed, the risks would need review. No season, road condition or regulation is claimed to have been researched. In one line, the three risks were chosen by testing the assumptions behind the objectives, the assessment was kept qualitative, and consequences and ownership were made visible without writing a full risk plan.

  • In practice, the risks would be validated by consulting school representatives, the NGO, suppliers and the carrier, reviewing relevant lessons, and testing the stock, cost and access assumptions. None of this is claimed to have happened.
  • Delphi is worth understanding, but it is not needed for a charter this small.

Study explanation of a proposed academic charter and its companion guide, read against the supplied Week 3: The Project Charter course deck. Open the source notes above to see which document each claim comes from.