Framing the risks
These are the initial risks that most directly threaten timely delivery, affordability and beneficiary value. Likelihood and impact are qualitative planning judgements, not measured probabilities, and detailed assessment follows authorization. The charter records the main uncertainties and who monitors them, and leaves a full risk plan for later.
Read with careThe deck's page 35 slide says “Quantitative Impact Summary”, but its notes on page 36 and pages 42-43 describe a high, medium or low assessment without detailed statistics. The charter follows the notes and does not manufacture numeric probabilities.
Three risks at a glance
All three are rated medium likelihood and high impact. Two are external and one is internal.
| Risk | Class | Monitor | Escalation trigger |
|---|---|---|---|
| R1 · Domestic delivery disruption | External | NGO logistics coordinator | Forecast delivery or replacement beyond Week 6 |
| R2 · Prices or delivery charges exceed allowances | External | Project Manager, supported by finance | Forecast above USD 9,200 needs immediate sponsor review |
| R3 · Inadequate validation of school needs and readiness | Internal: project engagement and requirements validation | NGO education coordinator | Missing approvals block purchasing; unresolved suitability or access concerns block final acceptance |
R1: domestic delivery disruption
If transport availability, road access or handling conditions differ from the assumptions, deliveries may arrive late, incomplete or damaged, preventing acceptance of 2,000 usable books within six weeks. It is prioritized because every school depends on physical delivery, even with in-country sourcing.
- Monitor: the NGO logistics coordinator.
- Initial response: validate access and receiving arrangements, confirm protective packing, and identify an alternative domestic carrier. Receipt is targeted for Week 5 so that Week 6 can absorb corrections.
- Escalation: when forecast delivery or replacement goes beyond Week 6.
R2: prices or delivery charges exceed allowances
If book prices or transport charges exceed the assumptions, the cash ceiling may be breached or the full collection may become unaffordable. The USD 6,000 book allowance is most of the base estimate, so extra fees could consume the contingency.
- Monitor: the Project Manager, supported by finance.
- Initial response: obtain inclusive quotations, compare alternatives, and monitor the forecast before ordering. In-scope responses may use contingency within delegated limits.
- Escalation: a forecast above USD 9,200 needs immediate sponsor review. Fewer books or lower quality are not acceptable unapproved savings.
R3: inadequate validation of school needs and readiness
If the team buys without meaningful school input or confirms handover too late, books may be unsuitable, allocations disputed or pupil access unavailable. The project could hit a transport target and still fail its intended value.
- Monitor: the NGO education coordinator.
- Initial response: obtain the Week 1 agreement, verify custodians and access, and involve teachers in acceptance.
- Escalation: missing approvals block purchasing, and unresolved suitability or access concerns block final acceptance.
The assumption behind each risk
Each risk applies the deck's assumption-testing method: any assumption that proves false may be a significant risk. Reading the three together shows which objective each one protects.
| Risk | Assumption tested | Objective threatened |
|---|---|---|
| Domestic delivery disruption | Road access, handling and carrier availability will support delivery | Quantity, quality and Week 6 completion |
| Prices or charges exceed allowances | The assumed book and transport allowances will be sufficient | The USD 9,200 ceiling and full delivery |
| Inadequate validation of school needs and readiness | Recipient agreement and access will be established before commitments | Suitability, participation and useful handover |
Against the deck's checklist
The deck lists what a charter risk entry typically records. This charter covers each element.
| The deck's element | In this charter |
|---|---|
| High-level description | An if-then statement for each risk |
| Internal or external classification | R1 and R2 external; R3 internal |
| Impact summary: high, medium or low | Medium likelihood and high impact, rated qualitatively |
| Assumptions and dependencies that may trigger it | The assumption each risk tests, and the charter's Section 4 |
| Risk ownership, which is optional | A named monitor, by role, for each risk |
Why R3 is internal
The first two risks are external because their triggers are carrier conditions and supplier charges. R3 is framed as internal because the specific failure is the team's own inadequate engagement and validation, which fits the deck's process category of internal risk.
Read with careCalling R3 internal does not claim that school behaviour is controllable. It classifies the team's own validation process, not the schools.
What was not copied, and how to validate
Customs delays from the brief's examples were left out, because international shipping is excluded; if the sourcing changed, the risks would need review. No season, road condition or regulation is claimed to have been researched. In one line, the three risks were chosen by testing the assumptions behind the objectives, the assessment was kept qualitative, and consequences and ownership were made visible without writing a full risk plan.
- In practice, the risks would be validated by consulting school representatives, the NGO, suppliers and the carrier, reviewing relevant lessons, and testing the stock, cost and access assumptions. None of this is claimed to have happened.
- Delphi is worth understanding, but it is not needed for a charter this small.