The Delphi technique
Delphi is an additional way to identify risks. Participants are unknown to each other, so ideas can be put forward without fear of ridicule.
- A moderator sends the question electronically to each participant.
- Each participant generates ideas and sends them back to the moderator.
- The moderator combines all responses into one list and shares it for comment.
- Comments return to the moderator, and the rounds continue until a general consensus is reached.
A qualitative risk matrix
Once risks are identified, the team estimates each one's likelihood, meaning how probable it is, and its consequences, meaning the potential impact on the project. The estimate usually comes from expert judgment or stakeholder interviews. The deck's matrix is a simple two-by-two grid, with its high-likelihood, high-consequence corner in red, and it lets the team rank risks as high, medium, or low.
Read with careThe slide labels only the likelihood axis. The consequence dimension comes from the speaker notes.
No statistics yet
At charter stage there is no detailed statistical or quantitative analysis. Those techniques come later in the project lifecycle. The aim now is to flag the most critical risks and start planning early awareness or mitigation.
Prioritizing risks
Prioritization ranks risks by the probability of occurring and the impact if they materialize, so the team focuses on the greatest threats. In the deck's example, technical risks such as unproven technology or integration challenges may be high in both probability and impact, so they receive high priority. Generic risks such as acts of God, like natural disasters, are often given low priority.
Read with careThe deck explains the low priority of natural disasters as their being unlikely or outside the team's control. Controllability is not one of the two ranking factors the deck names, so treat that reason with care.