Project Management · Module 3Lesson 6

Study explanation · Lesson 06 · 16 min

Stakeholders in the charter

Stakeholder management runs through the whole project, but the charter captures an early snapshot and uses power, interest, legitimacy, and urgency to decide who needs attention.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

Who counts as a stakeholder

The deck defines a stakeholder as any party, whether a group or an individual, that has an interest in the project or is affected by it. Stakeholders can be internal, such as the business unit, or external, such as the communities living around the project.

A continuous process

Stakeholder management runs throughout the project. The deck shows it as a flow of twelve steps.

  • Identify all of them, then determine their requirements, expectations, and interests.
  • Determine their level of influence and level of authority, and incorporate their values.
  • Plan how to engage them, and plan communication.
  • Manage expectations, influence, and engagement, communicate with them, and monitor communication and involvement.

The charter's snapshot

Detailed stakeholder analysis comes later. In the charter, the aim is a high-level view of who the stakeholders are, who must be informed, consulted, or involved from the start, and a foundation for engagement planning, so that no major voice is missed. It usually covers only the most critical stakeholders:

  • Names or roles, such as IT Director or Product Owner.
  • Position or department.
  • Level of influence or interest: high, medium, or low.
  • Primary concerns or interests, to anticipate support or resistance.
  • Engagement needs, such as regular updates or approval authority.

The power/interest grid

One key method classifies stakeholders by power, their ability to approve budgets, change scope, or set direction, and by interest, how engaged or affected they are. Where a stakeholder sits decides the engagement approach.

Power/interest grid · Source slides 53-55
PowerLow interestHigh interest
High powerActively consultRegularly engage
Low powerKeep informedMaintain interest

Read with careThe speaker notes say low-power, low-interest stakeholders can be monitored with minimal effort, while the grid labels that corner keep informed. The lesson follows the grid's labels.

The salience model

The salience model classifies stakeholders on three attributes: legitimacy, meaning how appropriate and recognized their involvement is; power, their ability to influence outcomes; and urgency, how far their needs require immediate attention. Stakeholders with all three are the most salient and get the highest priority.

Stakeholder types in the salience diagram · Source slides 56-57
AttributesLabel in the diagram
Legitimacy, power, and urgencyDefinitive
Power and legitimacyDominant
Power and urgencyDangerous
Legitimacy and urgencyDependent
Legitimacy onlyDiscretionary
Urgency onlyDemanding
Power onlyDemanding, repeated in the diagram

Read with careThe diagram labels both the power-only and urgency-only areas as demanding stakeholders, so the power-only area has no separate name in this deck.

Study explanation based on the supplied Week 3: The Project Charter source deck. Open the source notes above for slide-level traceability.