Who counts as a stakeholder
The deck defines a stakeholder as any party, whether a group or an individual, that has an interest in the project or is affected by it. Stakeholders can be internal, such as the business unit, or external, such as the communities living around the project.
A continuous process
Stakeholder management runs throughout the project. The deck shows it as a flow of twelve steps.
- Identify all of them, then determine their requirements, expectations, and interests.
- Determine their level of influence and level of authority, and incorporate their values.
- Plan how to engage them, and plan communication.
- Manage expectations, influence, and engagement, communicate with them, and monitor communication and involvement.
The charter's snapshot
Detailed stakeholder analysis comes later. In the charter, the aim is a high-level view of who the stakeholders are, who must be informed, consulted, or involved from the start, and a foundation for engagement planning, so that no major voice is missed. It usually covers only the most critical stakeholders:
- Names or roles, such as IT Director or Product Owner.
- Position or department.
- Level of influence or interest: high, medium, or low.
- Primary concerns or interests, to anticipate support or resistance.
- Engagement needs, such as regular updates or approval authority.
The power/interest grid
One key method classifies stakeholders by power, their ability to approve budgets, change scope, or set direction, and by interest, how engaged or affected they are. Where a stakeholder sits decides the engagement approach.
| Power | Low interest | High interest |
|---|---|---|
| High power | Actively consult | Regularly engage |
| Low power | Keep informed | Maintain interest |
Read with careThe speaker notes say low-power, low-interest stakeholders can be monitored with minimal effort, while the grid labels that corner keep informed. The lesson follows the grid's labels.
The salience model
The salience model classifies stakeholders on three attributes: legitimacy, meaning how appropriate and recognized their involvement is; power, their ability to influence outcomes; and urgency, how far their needs require immediate attention. Stakeholders with all three are the most salient and get the highest priority.
| Attributes | Label in the diagram |
|---|---|
| Legitimacy, power, and urgency | Definitive |
| Power and legitimacy | Dominant |
| Power and urgency | Dangerous |
| Legitimacy and urgency | Dependent |
| Legitimacy only | Discretionary |
| Urgency only | Demanding |
| Power only | Demanding, repeated in the diagram |
Read with careThe diagram labels both the power-only and urgency-only areas as demanding stakeholders, so the power-only area has no separate name in this deck.