Risk means uncertainty
When a charter lists risks, it is naming uncertainty: events or conditions that, if they materialize, could affect the project's ability to meet its objectives. If the objectives are not met, the business case itself may be jeopardized, meaning the value or justification for the project could be lost.
Internal and external risks
For discussion purposes, the deck sorts risks into two categories.
- Internal risks start within the project team or organization and are generally more controllable: technical risks such as technology failures, organizational risks such as team turnover, and process risks such as poor planning.
- External risks come from the outside environment and are typically beyond the team's control: regulatory risks such as changes in laws, and market risks such as new competitors.
Stay high level
A charter is not a full risk management plan. It gives a high-level snapshot that acknowledges uncertainty early and aligns stakeholders on what could go wrong. It typically records:
- A high-level description of each key risk.
- Whether the risk is internal or external.
- A summary of its potential impact.
- The assumptions and dependencies that could trigger or influence it.
- Optionally, who owns or monitors it.
Read with careThe slide calls the third element a quantitative impact summary, but its notes describe impact noted as high, medium, or low, and the deck later says no detailed quantitative analysis happens at this stage. At charter stage, expect a high-level impact rating rather than numbers.
Five ways to collect early risks
Because the project is still early, risk gathering captures major uncertainties rather than detailed assessments.
- Stakeholder interviews, asking “What concerns you most?” and “What could go wrong?”
- Lessons learned from similar projects, which reveal recurring risks such as missed deadlines or technology issues.
- Assumption testing, because any assumption that proves false may be a significant risk.
- An environmental scan for external risks, such as market or regulatory changes, and internal ones, such as resource constraints.
- Expert judgment from experienced project managers or PMOs.