Case source guide

Applied case: a project organigram for an AI transformation

Where each part of this case comes from, and how its Week 5 page references stand against the course deck.

The two documents

The case reads a two-page submission, an organizational chart with a written justification of about six hundred words, together with the author's companion analysis, which is written for personal study and is not part of the assessed work. Paragraph and section numbers refer to those documents. Neither is republished here, and neither describes a real bank.

Why there is a deck check

Both documents cite the Week 5 deck by PDF page. That deck is in this library, so every reference was checked against the actual pages and the result is published below. The check is this case's own work. Open the Week 5 lessons

Case map · Submission, Analysis and Deck
Case partSubmissionAnalysisCourse lessons applied
1 · The briefChart title, scope note§1-4Week 5: organigrams, integrated teams
2 · The organigramChart, key, scope note§2, §4, §5.1Week 5: organigrams, organizational structure
3 · Why a matrix¶1-3§5.1-5.2Week 5: organizational structure, integrated teams and roles
4 · Reporting lines¶4-6§4, §5.2, §7Week 5: organigrams, generations, management theories
5 · Decision rights¶6-7§6Week 5: integrated teams and roles, organizational structure
6 · Assumptions and defence¶6-7§4, §7Week 5: types of project teams, integrated teams

Read with careThe analysis numbers only its first three sections. The later headings are numbered here: §4 source-to-design map, §5 design choices and trade-offs, §6 how the structure operates, §7 assumptions and defence.

Week 5 references checked against the deck
Claim in the submission or analysisDeckResult
Core members need time and authority; project integration differs from sponsorship and resource managementpp. 3-16Matches
Sponsorship includes championing the project and protecting it from unnecessary changepp. 12-13Matches
Functional managers keep staffing, development and departmental standardspp. 14-16Matches
Matrix risks of competing priorities and unclear accountabilitypp. 76-77Matches
Answered by decision limits, resource agreements and escalationp. 77Matches the deck's remedies: role clarity, alignment meetings, escalation protocols
Functional: clear reporting and deep expertisepp. 63-66Matches
Projectized: strong authority and speed, but duplicated resources and weaker continuitypp. 67-70Matches
Matrix chosen for this context, not because it is always bestpp. 71-79Matches: the deck says there is no single best structure
A matrix with strong project leadershipp. 72Consistent, with care: the deck names a strong matrix only in its notes and defines none of the variants
Coaching, two-way communication, mentoring; support adapted to individuals, not agepp. 39-48Matches
A dedicated core with agreed departmental contributionspp. 21-27Matches
Theory Y and Herzberg's responsibility support delegated workpp. 54-59Matches
Boxes, lines and levels; readabilitypp. 87-88Matches
The dotted line means risk escalationpp. 87-92Narrower than the deck, which uses dotted lines for advisory or functional oversight; the analysis says so
Align people with the project scopepp. 93-94Matches
No program or portfolio managers just because the project is largepp. 18-19Consistent
The project manager delegates project work without holding staffingpp. 10-11Consistent: in charge of the project, not necessarily the resources

Read with careNo contradiction with the deck was found. The one narrowing, the dotted line, is declared in the analysis itself.

Part 01

The brief, and what it really tests

The assignment asks how people and decisions are organized for one AI project that crosses three departments. It is a test of clear responsibility, authority, coordination and reporting, and its own brief contains an ambiguity worth naming.

Open the case part
What the assignment asks

One cross-departmental AI project; not architecture, model selection, a schedule or a bank-wide chart.

Analysis §1
The ambiguity

Three levels requested; four titles in the example; the three-band reading and its limits.

Analysis §2 · Submission chart scope note
The deliverable

A chart page and a justification page with a course reference; the analysis stays separate.

Analysis §3 · Submission pp. 1-2
Three sources

From the assignment, from Week 5, and applied to the scenario.

Analysis §4

Part 02

Reading the three-level organigram

The chart places an executive sponsor over a project manager, three specialist leads and five operational teams, with one dotted route back to the top. Reading it the way the deck teaches shows what each line carries and what the chart leaves out on purpose.

Open the case part
The chart

Three bands, ten role boxes, the department band, the key and the scope note.

Submission chart
How to read an organigram

Start at the top, follow the lines, read dotted lines as advisory, look for bottlenecks.

Deck pp. 91-92
Elements and creation

Boxes, solid and dotted lines, levels; define the scope first and validate before sharing.

Deck pp. 87-90 · Analysis §4
The narrower dotted line

Defined as risk escalation, against the deck’s advisory or functional oversight.

Analysis §4 · Deck p. 87
Project-only view

Not a complete human-resources matrix chart; functional reporting continues.

Submission scope note · Analysis §5.1

Part 03

Why a matrix, and who sponsors it

The submission chooses a matrix with strong project leadership, weighs it against functional and projectized options, and answers the matrix’s known weaknesses. At the top, it proposes a sponsor who also chairs the steering committee.

Open the case part
Structure and purpose

A matrix with strong project leadership, connecting departments without competing AI projects.

Submission ¶1 · Deck pp. 71-77
The option table

Functional, projectized and matrix, each with its benefit and its trade-off here.

Analysis §5.1 · Deck pp. 63-77
The sponsor

Championing and protecting the project, not only financing it; a shared role is possible.

Submission ¶2 · Deck pp. 12-13
Resources and authority

Functional managers keep staffing and standards; limits agreed at initiation.

Submission ¶3 · Deck pp. 10-11, 14-16
Matrix challenges

Conflicting priorities, ambiguity, delays, two bosses; role clarity, alignment and escalation.

Deck pp. 76-77 · Submission ¶3, ¶7

Part 04

Each reporting line, and why

Every line in the chart was a choice. The analysts report to the project manager to keep business outcomes central, the technical teams share one parent, adoption is led from the management band, and risk advice has its own route.

Open the case part
Operational accountability

Technical teams under one lead; analysts under the project manager.

Submission ¶4 · Analysis §5.2
Change and adoption

Coaching, two-way communication and mentoring, adapted to individuals.

Submission ¶5 · Deck pp. 45-48
Risk and escalation

Officer, analysts and the dotted route; two meanings of risk.

Submission ¶6 · Analysis §5.2
Theories behind delegation

Theory Y and Herzberg’s responsibility support delegated specialist ownership.

Analysis §4 · Deck pp. 54-59
Bottlenecks

The deck’s test for one person with many direct reports, applied here by this case.

Deck pp. 91-92 · Analysis §7

Part 05

Decision rights, and a pilot that goes wrong

A chart is only useful if people know what they may decide. The analysis proposes a decision boundary for each role, then walks a customer-service pilot through the structure when testing reveals a problem.

Open the case part
Decision boundaries

Five roles, each with a proposed limit to be confirmed in the charter.

Analysis §6
The pilot illustration

Inconsistent responses in testing, handled in four steps.

Analysis §6
Readiness evidence

Technical testing, business acceptance, staff readiness and risk review before rollout.

Submission ¶6 · Analysis §6
Project manager control

Measuring performance, variances and change requests including corrective action.

Deck pp. 10-11
Coordination

Integrated review, shared plan, decision record; alignment meetings and escalation protocols.

Submission ¶7 · Analysis §6 · Deck p. 77

Part 06

Assumptions, scale and defending the design

The design rests on five stated assumptions, a team with real time and authority, and a way to grow without new executive layers. The analysis ends with short answers to the questions an assessor is likely to ask.

Open the case part
Assumptions

One project, the sponsor and chair, agreed authority and time, functional reporting, no jurisdiction.

Analysis §7
Team allocation

Dedicated core plus agreed departmental contributions.

Submission ¶7 · Analysis §4 · Deck pp. 3-5, 21-27
Scalability

More teams under existing leads; review if workloads become excessive.

Submission ¶7 · Analysis §7 · Deck pp. 78-79
Programs and portfolios

Not added simply because the project is large.

Analysis §7 · Deck pp. 18-19
Defence answers

Four likely challenges answered in the first person.

Analysis §7
Source limits

No regulation, AI standard or approval process is sourced.

Submission ¶6 · Analysis §4, §7

Source appendix

Where these documents need a careful reading

Read with care

Three levels, four titles

The brief asks for three levels while its example chains four positions. The submission groups them into three governance bands and states that reading in its scope note. It is defensible, but an assessor could read the brief differently.

A narrower dotted line

The chart uses its dotted line only for escalating unresolved risk concerns. The deck describes dotted lines as advisory or functional oversight. The companion analysis notes the difference itself.

Strong is not a deck definition

The deck names weak, balanced and strong matrices only in its speaker notes and defines none of them. A matrix with strong project leadership is the author's description of this design.

Two classifications

Organizational structures are functional, projectized or matrix; organigram types are hierarchical, matrix or flat. The chart is a hierarchical drawing of a project that sits inside a matrix organization, and the case keeps the two apart.

CTO means Chief Transformation Officer

The analysis shortens the sponsor's title to CTO, which readers commonly take for chief technology officer. The case spells the title out every time.

Two kinds of risk

The risk and compliance officer is a project role. Risk management is one of the three departments receiving the AI solutions.

No jurisdiction

No country, regulator, banking regulation or AI standard is named or sourced. The risk-review and escalation arrangements are design proposals, not a compliance certification.

A proposal, not a bank

No existing bank's structure is described. The sponsor arrangement, the decision boundaries and the customer-service pilot are the author's proposals and illustration.

The brief is second-hand

The assignment brief is not in this library. Its requirements are known only as the companion analysis reports them.

Checked against the submission, the companion analysis and the Week 5 deck.

What not to take away

The case parts actively work against these misreadings:

  • Three governance levels means three job titles on every path.
  • Each department receiving the change needs its own hierarchy.
  • A dotted line always means escalation.
  • The project chart shows everyone's whole reporting picture.
  • A matrix is always the best structure for a large project.
  • Strong matrix is a term the deck defines.
  • The project manager owns the specialists' staffing and development.
  • Business analysts belong under the technical lead because the project is about AI.
  • Change management can start after the system is built.
  • Executive approval proves technical or compliance readiness.
  • A launch date is evidence that a concern has been resolved.
  • A large project automatically needs program or portfolio managers.

Study-guide synthesis; each item is addressed in the parts.