An organigram needs decision rights
The analysis puts it plainly: the organigram is useful only if people understand what they may decide. It proposes a boundary for each key role, to be confirmed in the project charter.
| Role | Proposed decision boundary |
|---|---|
| Sponsor and steering committee | Approve funding, strategic priorities and material scope changes, and resolve conflicts beyond delegated authority. Act on specialist advice rather than treating approval as proof of readiness. |
| Project manager | Integrate the plan, coordinate dependencies and manage delivery within approved limits. Agree resources with functional managers and escalate exceptions. |
| Technical lead | Direct technical design, model development, integration and deployment preparation within scope. Provide testing evidence and surface defects. |
| Change management lead | Direct training, communication and adoption. Report readiness gaps and user feedback so they can shape delivery decisions. |
| Risk and compliance officer | Coordinate review evidence, document concerns, and recommend remediation or a hold. Escalate unresolved issues directly to the sponsor. |
Applied choiceThese boundaries are the author’s proposals for the charter. The scenario supplies none of them.
A pilot that goes wrong
To show the structure working, the analysis imagines a customer-service AI pilot whose testing reveals inconsistent answers to customer questions. Each team sends its findings through its own named reporting line.
- Define and build. Business analysts clarify the required behaviour with customer-service representatives, the technical lead directs the fix and testing, and IT support prepares a controlled environment.
- Test adoption and review concerns. Training staff observe real use and capture feedback, while risk and compliance analysts document their review findings.
- Coordinate the decision. The project manager records the issue, brings the leads together and coordinates the corrective work, and the risk officer can escalate an unresolved concern to the sponsor.
- Reassess readiness. Technical evidence, business acceptance, staff readiness and risk findings are brought together before the designated authority decides on rollout.
Read with careThe pilot is an illustration of how the structure could work. It is not a committed deliverable of the project, and it is not a use case from the course.
Readiness is evidence, not a date
Before rollout, the submission requires four things to be evidenced: technical testing, business acceptance, staff readiness and risk review. In the pilot, a schedule target alone is never treated as proof that an outstanding concern has been resolved.
- Lesson 1 says the project manager controls the project by measuring performance against the plan and determining the need for change requests, including corrective action.
- The sponsor’s boundary asks for action on specialist advice, so executive approval is not mistaken for technical or compliance readiness.
Key ideaA date tells you when a decision is due. Only evidence tells you which decision is right.
Coordination without bureaucracy
The analysis proposes a regular integrated review of progress, dependencies, risks and adoption, supported by one shared plan and a decision record. Routine matters stay with the appropriate lead, material exceptions move to the project manager or the sponsor, and urgent risk concerns use the dotted route instead of waiting for a meeting.
- This applies the deck’s matrix remedies of regular alignment meetings and agreed escalation protocols.
- The analysis deliberately stops short of inventing a mandatory meeting calendar that the scenario does not support.
Key takeaways
- A chart only works when each role knows what it may decide, so each key role has a proposed boundary.
- In the pilot, every team reports findings through its own named line.
- The project manager coordinates the response; the risk officer can still go directly to the sponsor.
- Rollout needs technical, business, staff and risk evidence together, and a schedule target is not evidence.
- One shared plan, an integrated review and a decision record keep coordination light.