Project Management · Module 5Applied casePart 3

Applied case · Part 03 · 16 min

Why a matrix, and who sponsors it

The submission chooses a matrix with strong project leadership, weighs it against functional and projectized options, and answers the matrix’s known weaknesses. At the top, it proposes a sponsor who also chairs the steering committee.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

Three structures weighed

The analysis weighs each structure the deck teaches against this one project. Each has a real benefit, and each has a cost that matters here.

The structural options for this project · Analysis §5.1, Deck pp. 63-77
OptionBenefit from Week 5Trade-off for this project
FunctionalClear departmental reporting and deep specialist expertiseThree departments could pursue separate priorities, with a project manager too weak to integrate them
ProjectizedStrong project-manager authority, focus and fast executionIt could duplicate specialists and weaken continuity with the bank’s permanent teams
Matrix, selectedShared expertise and cross-functional collaborationIt adds dual-authority risks, so resource commitments, decision limits and escalation must be explicit

Key ideaThe analysis calls the choice contextual, not a claim that a matrix is always best. That matches the deck’s closing video, which says there is no single best structure.

What strong project leadership means here

The project manager directs the agreed project work, while the functional managers keep staffing, professional development and departmental standards. The specialist leads report to the project manager for project coordination only.

  • This follows the deck’s point that the project manager is in charge of the project, but not necessarily the resources.
  • It also follows the functional manager’s role in the deck: assigning qualified staff, development and compliance with departmental standards.
  • The submission asks for resource availability and decision limits to be agreed at initiation, rather than assuming unlimited authority.

Applied choiceCalling the arrangement a matrix with strong project leadership is the author’s description of the balance of power in this design.

Read with careThe deck names weak, balanced and strong matrices only in its speaker notes and does not define them. Read the phrase as the author’s description, not as a course definition.

The sponsor and the steering committee

At the top, the project sponsor sits within an executive steering committee. The committee approves funding, strategic priorities and major scope changes, resolves conflicts between departments and confirms the intended benefits. Routine delivery decisions stay below it.

  • The deck says sponsorship goes beyond funding: the sponsor champions the project, offers strategic guidance and protects it from unnecessary change.
  • The deck also says the sponsor role can be shared by two or more people working together, which a committee makes visible.
  • Combining the sponsor and chair roles gives the project one clear executive interface, while the committee stays the decision body.

Applied choiceThe Chief Transformation Officer as sponsor and committee chair is the author’s proposed arrangement, not a description of any existing bank.

Read with careThe companion analysis later shortens the title to CTO. Readers often take those letters to mean a chief technology officer, so this case always spells the title out.

Answering the matrix’s known weaknesses

Lesson 5 lists the matrix’s challenges and the remedies for them. The design answers each one with something specific, and the table below pairs them.

Deck challenges and the design’s responses · Study-guide mapping of Deck pp. 76-77 to Submission ¶3, ¶7
Challenge the deck namesHow the design responds
Conflicting priorities between project and functionResource availability is agreed with functional managers at initiation
Role ambiguityEach role has a stated decision boundary, and decisions are recorded
Decision delays from seeking consensusLeads resolve routine matters within agreed limits
Employees torn between two bossesEach operational team has one clear project reporting line
The need for escalation protocolsThe project manager escalates material exceptions, and the risk officer has a direct route

Key takeaways

  • Functional could leave three departments with separate priorities; projectized could duplicate specialists and break continuity.
  • The matrix is chosen for this context, not because it is always best.
  • The project manager directs project work; functional managers keep staffing, development and standards.
  • Strong project leadership is the author’s description, because the deck names but does not define a strong matrix.
  • The sponsor chairs a steering committee that takes the strategic decisions and leaves routine delivery below.

Study explanation of a proposed academic project organigram and its companion analysis, read against the supplied Week 5: The Project Team course deck. Open the source notes above to see which document each claim comes from.