Planning & Controls · 19 November session reference
Glossary
Short definitions as the module uses them, each linked to the lesson it comes from.
- Resource allocation
Assigning a resource to an activity and estimating the effort or units it needs.
Review Lesson 1- Resource loading
Adding a resource’s assigned demands in each period so they can be compared with availability.
Review Lesson 1- Resource overload
Demand above a resource’s available capacity in a relevant period.
Review Lesson 1- Renewable resource
A resource whose capacity is available again in subsequent periods, such as crew working hours.
Review Lesson 1- Non-renewable resource
A limited stock consumed by the work within the planning boundary, such as the example’s steel beams.
Review Lesson 1- Doubly constrained resource
A resource arrangement needing both a period-capacity check and a cumulative consumption check.
Review Lesson 1- Work Breakdown Structure (WBS)
The breakdown identifying the project work that must be assigned and planned.
Review Lesson 2- Organizational Breakdown Structure (OBS)
The organizational structure identifying the teams and people who can be connected to work responsibilities.
Review Lesson 2- RACI
Responsible, Accountable, Consulted and Informed: roles used to connect work items with people and teams.
Review Lesson 2- Worker-week
An effort unit representing one person’s work for one week under the example’s working assumptions.
Review Lesson 3- Time-phased capacity
The available resource capacity organized by the periods in which work needs it.
Review Lesson 3- Total float
The scheduling flexibility available without delaying the project finish under the current model’s assumptions.
Review Lesson 3- Priority rule
A practical basis for choosing which ready activity receives a scarce resource, such as lower total float or waiting successors.
Review Lesson 3- Resource smoothing
Adjusting activity timing within available flexibility while preserving the planned project finish.
Review Lesson 5- Resource leveling
Adjusting the schedule to respect resource availability, potentially changing activity dates and the project finish.
Review Lesson 5- Added capacity
An approved change in available resources, such as another machine, a suitable additional worker or another shift.
Review Lesson 5- Time-related cost
A cost whose amount can change with the duration, such as continuing supervision, rental or overhead in the class discussion.
Review Lesson 6- Resource cost
The cost of the people, equipment or other resources actually used, including changes such as hiring or an extra shift.
Review Lesson 6- Productivity assumption
An estimate of output relative to resource effort that needs relevant evidence before it is used to change a schedule.
Review Lesson 7- Token budget
The allocation for model or agent usage raised in the AI discussion as a resource and cost consideration.
Review Lesson 7