The work and the organization need a connection
Before assigning hours, the lecturer asks who does what. The Work Breakdown Structure, or WBS, identifies the work. The Organizational Breakdown Structure, or OBS, identifies the organization’s teams and people. Seeing the work in one structure and the people in another does not yet establish who acts on a particular work item. The session uses a RACI matrix to make that connection. Its rows represent work items from the WBS and its people or team entries come from the OBS. The matrix clarifies who is Responsible, Accountable, Consulted and Informed for each item.
- WBSIdentify the work items
- OBSIdentify teams and people
- RACIConnect each work item with its roles
Roles describe different kinds of involvement
The recording expands all four RACI letters and illustrates a foreman responsible for measuring installed quantities while being informed about preparing the cost forecast. These are different kinds of involvement in two different work items. Being kept informed about a forecast does not mean the foreman must prepare it. Study-guide clarification: Responsible describes doing the work, Accountable identifies the role answerable for its completion, Consulted contributes input, and Informed receives the relevant update. Agree those meanings with the team so that a matrix resolves uncertainty instead of becoming another list of names.
| Role | Study-guide explanation | Application |
|---|---|---|
| Responsible | Carries out the work | The foreman measures installed quantities in the example |
| Accountable | Answers for completion and the result | Identify this role explicitly for the work item |
| Consulted | Provides input needed for the work or decision | Seek the relevant contribution before the decision |
| Informed | Receives the relevant communication | The foreman receives information about the cost forecast |
An assigned name still needs a feasible workload
Study-guide synthesis: responsibility and capacity are complementary checks. A matrix can make ownership clear while the named person remains overloaded. Once roles are agreed, estimate the effort and check when that person can actually do the work. For the engineer from Lesson 1, clarifying who owns the drawing review and inspection would be useful, but it would not remove the two-hour Monday overload. A workable plan needs both clear responsibility and realistic availability.
Key ideaFirst make the responsibility explicit, then check whether the assignment fits the resource calendar.
Key takeaways
- WBS describes the work; OBS describes teams and people.
- RACI connects work items with responsible, accountable, consulted and informed roles.
- Clear ownership and feasible loading must both be checked.