Project Planning, Scheduling and Controls - FA26-27 · Class recording · 19 November 2026

Can the available resources deliver the schedule?

Connect assignments, period loads, responsibility and float to a feasible plan, then explain the timing and cost trade-offs.

Study the complete fourth live session: allocation and loading, resource types, WBS–OBS–RACI, worker-week capacity, equipment priorities and the compressor example. The learner Q&A extends the distinction between smoothing and leveling to finance, cost and AI-assisted work.

  • Allocation and loading
  • Resource limits
  • WBS, OBS and RACI
  • Period capacity
  • Priority rules
  • Smoothing and leveling
  • Cost trade-offs
  • AI productivity

Module introduction

The dates need a resource plan that can actually run.

The lecturer identifies this fourth live session as Week 4 and starts with a practical conflict: two ready activities need seven compressors while the site has only six. Seven lessons follow the resource reasoning from individual assignments to the cost and productivity questions raised by learners. The guide preserves the spoken quantities and identifies the clarifications needed when informal wording could imply that every leveling exercise delays a project or that adding staff defines smoothing.

The resource decision developed in the session
  1. AssignWork, people and required effort
  2. LoadCombined demand in each period
  3. AdjustFloat, priorities and resource limits
  4. ExplainFinish, cost and remaining assumptions

Your learning path

Your path through the 19 November class

Open source guide
01Allocation and loadingDistinguish assigning a resource to an activity from adding its demand across the day, then check the kind of capacity the resource actually has.7 min02WBS, OBS and RACIConnect the work breakdown, organizational teams and responsibility assignments before treating an hours estimate as an executable plan.6 min03Capacity and prioritiesUse the worker-week example to distinguish total availability from a period overload, then apply float and successor considerations to a resource conflict.7 min04The compressor exampleFollow the spoken compressor conflict and the reported move of D, while distinguishing the lecturer’s example from a fully reconstructed network calculation.7 min05Leveling versus smoothingDistinguish protecting the finish through available flexibility from resolving resource limits even when the completion date may have to change.7 min06Finance and cost Q&AApply the session’s finance example and explain why direct resource cost, duration-related cost and penalties need separate consideration.7 min07AI and resource planningRead the closing AI discussion as a productivity and resource-planning conversation, with token costs, verification and human judgment kept in the plan.6 minA feasible plan connects work, capacity and a clear trade-offAllocate the work, add the loads in each period and check them against the right resource limit. Use flexibility and priority rules carefully, distinguish smoothing from leveling, and explain the actual finish-date and cost consequences of the proposed plan.Summary