The totals pass while Week 5 fails
The recording asks whether nine workers can complete a project in twelve weeks when the estimated effort is 101 worker-weeks. At that staffing level, nine multiplied by twelve gives 108 worker-weeks. The aggregate comparison appears comfortable, with seven worker-weeks more capacity than estimated effort. But Week 5 contains one activity needing six workers and another needing eight. Combined demand is fourteen workers while only nine are available, leaving a shortage of five workers in that week. Study-guide clarification: the seven worker-weeks of aggregate difference cannot be treated as five extra people immediately available in Week 5. Capacity must coincide with the work that needs it.
| Check | Calculation | Interpretation |
|---|---|---|
| Total availability | 9 workers × 12 weeks = 108 worker-weeks | A whole-project effort limit |
| Estimated project effort | 101 worker-weeks | Below the total availability |
| Aggregate difference | 108 − 101 = 7 worker-weeks | Potential spare capacity across the horizon |
| Week 5 demand | 6 + 8 = 14 workers | Above that week’s nine-worker limit |
| Week 5 shortage | 14 − 9 = 5 workers | A period conflict that the totals conceal |
Key ideaA feasible resource plan must fit the relevant capacity limits in every period.
Spare capacity helps only when work can move there
The lecturer asks whether quieter weeks can help. The answer is conditional: yes, if one of the overloaded activities can move to a week with spare capacity. A blank space on a histogram is useful only when the activity’s logic, timing and resource needs allow it to use that space. Study-guide clarification: check predecessors, successors and the activity’s full demand over its proposed new dates. A week with enough people in total may still lack a required skill or machine. A move that resolves one resource can also create a conflict for another. Review the complete proposed assignment before declaring the overload solved.
Less scheduling freedom usually gets priority
When two ready activities need the same machine, the recording asks which activity has less room to move. That room is total float: the amount an activity can move without delaying the project finish under the current schedule assumptions. With a zero-float activity and another that can wait three days, the lecturer would usually allocate the machine to the zero-float activity. If their flexibility is similar, look at what finishing each activity enables. The source suggests considering the number of waiting successors and teams. These are practical priority rules, not proof of an optimal solution. After changing the schedule, review the logic and resource loads again because the conditions supporting the first priority decision may change.
| Question | What the answer contributes |
|---|---|
| Are both activities genuinely ready? | Check their predecessor requirements before allocating the shared resource |
| Which has less total float? | Protect the activity with less scheduling freedom where appropriate |
| What does completing it enable? | Consider the successors and waiting teams when flexibility is similar |
| Does the revised plan remain feasible? | Check the new dates, finish and combined resource loads |
Read with careThe final feasibility check is study-guide synthesis. The lecture’s priority guidance does not establish a universal optimization rule.
Key takeaways
- Worker-weeks measure total effort; a weekly resource load tests timing.
- Week 5 needs fourteen workers against nine available, a five-worker shortage.
- Float and waiting successors help explain priority, but the resulting schedule still needs checking.