Seven compressors requested, six available
The site example has activities A through G and six compressors. C and D both follow B, so they become ready together after B completes. C needs five compressors and D needs two. Running them together demands seven compressors, one more than the available six. The lecturer identifies A–B–C–E–G as the critical path and gives a project duration of twenty days. C therefore has priority in the example: it is on that controlling path and has zero total float. Moving D is the proposed way to reduce the clash while protecting the finish.
| Item | Spoken value or relationship |
|---|---|
| Activities | A, B, C, D, E, F and G |
| Resource capacity | 6 compressors |
| C and D predecessor | Both follow B |
| Concurrent compressor demand | C needs 5; D needs 2; together they need 7 |
| Critical path stated | A–B–C–E–G |
| Project duration stated | 20 days |
| Proposed move | Move D to Days 11–14 |
Read with careThe full activity-duration and logic table is referred to on screen but is not spoken in full. These entries do not reconstruct all early and late dates.
Smoothing uses flexibility while keeping the finish
The lecturer reports that D can move to Days 11–14, when sufficient compressor capacity is available, while the project remains twenty days long. Resource smoothing uses an activity’s available flexibility to improve the load profile without moving the planned project finish. The broader explanation mentions a period already using three compressors. Adding D’s two would make five, within a capacity of six. That arithmetic illustrates the capacity test. The source does not narrate a complete period-by-period load table, so the study guide does not claim to independently verify the whole reported D move from the recording alone.
Key ideaA move counts as smoothing only when its timing remains feasible and the project finish is preserved.
Check the whole move, rather than copying its date label
Study-guide clarification: test D against its allowable dates, predecessor and successor restrictions, required resource units and every period of its proposed placement. Then check that other resources remain feasible and the finish stays at day twenty. Being noncritical does not mean an activity can be placed anywhere. Use the separate resource-allocation document path when you want the deck’s full numerical network and redrawn resource charts. This recording path preserves the shorter spoken explanation and its evidence boundary. A date range copied from a slide reference is a reported result until the relevant input network and time convention are available.
- D is ready when its new placement begins.
- Its duration and successors fit the permitted dates.
- Its full compressor demand fits the load in every affected period.
- The revised resource plan still completes in twenty days.
Key takeaways
- C and D together need seven compressors against six available.
- The session protects critical C and reports moving D to Days 11–14.
- The recording’s incomplete spoken network limits independent date verification.