Project Planning, Scheduling and Controls - FA26-27 · Class recording · 12 November 2026

How confident is the completion date?

From duration data and three-point estimates to changing critical paths, Monte Carlo and an agreed confidence level.

Study the complete 12 November class: descriptive statistics, estimation bias, normal models, the central limit theorem, PERT, Monte Carlo, distribution selection and percentile decisions. The learner Q&A also revisits network passes, SS+5, time conventions and hard versus soft logic.

  • Duration uncertainty
  • Estimation bias
  • Normal models and CLT
  • PERT
  • Monte Carlo
  • Distribution choice
  • Completion percentiles
  • Network Q&A

Module introduction

Keep the schedule logic. Make the uncertainty visible.

The lecturer introduces this recording as Week 3 and asks how confident a team should be in its planned finish. The seven lessons follow that question from the data through the model to a decision, then return to the network questions raised by learners. Numerical illustrations retain their source context. Mathematical extensions and corrections to informal Q&A wording are identified as study-guide clarification.

The session’s route from evidence to a schedule decision
  1. UnderstandData, conditions and estimation bias
  2. ModelDurations, network logic and shared risks
  3. ExplorePERT assumptions and Monte Carlo outcomes
  4. DecideAgree confidence, test actions and update

Your learning path

Your path through the 12 November class

Open source guide
01Uncertainty and the dataA ten-day activity estimate is useful for planning, but it does not describe the possible outcomes. The session begins with the center, spread and shape of duration data, then asks how evidence and estimation bias affect the dates we trust.9 min02Normal models and learningThe session explains the normal distribution with a ten-day mean and two-day standard deviation. Its later dice example clarifies the central limit theorem. Neither idea makes every project finish normally distributed, and neither removes the need to update a plan as knowledge improves.9 min03PERT and path riskPERT combines optimistic, most likely and pessimistic activity estimates. The session’s 8–10–16 example shows expected duration, standard deviation and variance. A useful calculation keeps its units straight and makes the assumptions behind any path probability visible.10 min04Monte Carlo and criticalityMonte Carlo simulation calculates many possible versions of a schedule. Each trial samples uncertain durations, recalculates the network and records its finish. The result is useful only when shared activities, dependencies and important common risks are represented consistently.9 min05Choosing distributionsThe lecture and Q&A compare triangular, beta-PERT, uniform and normal models. Historical records, expert judgment and the nature of the work guide the choice. Three estimates alone do not make all outcomes equally likely, and a cluster near an average does not prove normality.10 min06Percentiles and commitmentsThe recording’s illustrative P50, P80 and P95 dates make confidence visible. A later date can offer a higher modeled probability of completion, while the decision still depends on the cost of delay, assumptions and the actions available to reduce risk.8 min07Network Q&A and logicLearners return to forward and backward passes, date conventions, start-to-start links and hard versus soft logic. These questions reinforce the foundation of probabilistic analysis: durations vary inside a network whose calculations and relationships still need to be correct.10 minFrom an uncertain duration to an explained commitmentA sound completion forecast connects relevant data, sensible distribution assumptions and correct schedule logic. PERT can clarify an activity or fixed path, while Monte Carlo explores the whole network across many outcomes. Percentiles make the risk behind a proposed date visible.Summary