Planning & Controls · 12 November session reference

Glossary

Short definitions as the module uses them, each linked to the lesson it comes from.

Probabilistic schedule analysis

Analysis of possible schedule completion times and their modeled likelihoods under duration and risk assumptions.

Review Lesson 1
Mean

The arithmetic average: the sum of observations divided by their count.

Review Lesson 1
Median

The middle of ordered observations; four in the source’s five-duration example.

Review Lesson 1
Mode

The most frequent or most likely value; distinct from the mean.

Review Lesson 3
Standard deviation

A measure of spread around the mean, expressed in the original units of the observations.

Review Lesson 1
Variance

The square of standard deviation, expressed in squared units such as days squared.

Review Lesson 3
Skewness

Asymmetry of a distribution, such as a longer right tail allowing unusually long durations.

Review Lesson 1
Kurtosis

A distribution characteristic concerning tail weight and extreme observations.

Review Lesson 1
Optimism bias

Expecting fewer problems than the evidence supports.

Review Lesson 1
Anchoring

Excessive influence from the first estimate or number encountered.

Review Lesson 1
Availability bias

Giving excessive weight to a recent or memorable event when estimating.

Review Lesson 1
Normal distribution

A symmetric bell-shaped model described by a mean and standard deviation; its central 68–95–99.7 bands depend on that model.

Review Lesson 2
Central limit theorem

A result explaining how appropriately standardized sums or averages can approach a normal pattern under suitable conditions; not proof that every project finish is normal.

Review Lesson 2
Rolling wave planning

Progressive planning that gives near-term work more detail and elaborates later work as information becomes available.

Review Lesson 2
PERT

Program Evaluation and Review Technique; in this session, a three-point estimation method using (a + 4m + b) ÷ 6 for expected duration.

Review Lesson 3
Covariance

A measure of how two uncertain quantities vary together; covariance terms affect the variance of their sum when dependence matters.

Review Lesson 3
Z-score

For the fixed-path normal approximation, the deadline minus the path mean, divided by path standard deviation.

Review Lesson 3
Monte Carlo trial

One coherently sampled version of the uncertain schedule, recalculated to record its finish and controlling activities.

Review Lesson 4
Shared activity

One activity appearing in more than one path; it keeps one sampled duration throughout a given simulation trial.

Review Lesson 4
Shared risk

A common cause that can affect several activities and should be represented in the uncertainty assumptions when material.

Review Lesson 4
Triangular distribution

A bounded model defined by a minimum, mode and maximum, with density rising to and falling from the mode.

Review Lesson 5
Beta-PERT distribution

A smooth bounded distribution based on three-point estimates, typically using the PERT weighting toward the most likely value.

Review Lesson 5
Uniform distribution

A model giving equal probability to equal-sized intervals inside its bounds.

Review Lesson 5
Completion percentile

A date threshold at or before which a stated percentage of modeled project outcomes finish.

Review Lesson 6
P80

The completion threshold by which eighty percent of modeled outcomes finish, leaving twenty percent later under the model.

Review Lesson 6
Forward pass

Calculation of early dates through the network, honoring the governing predecessor restrictions.

Review Lesson 7
Backward pass

Calculation of late dates backward from a chosen project finish, honoring the governing successor restrictions.

Review Lesson 7
SS+5

A start-to-start relationship requiring the successor start to be at least five time units after the predecessor start.

Review Lesson 7
Hard logic

A mandatory work sequence arising from a physical or technical requirement.

Review Lesson 7
Soft logic

A preferred sequence chosen for the work, which may be reconsidered if another feasible arrangement is justified.

Review Lesson 7