Start with the simple forward pass, then respect every predecessor
A learner asks how to begin network calculations. The lecturer uses activity A with duration two days and an early start of zero: early finish is zero plus two, giving time two. If B and C follow A through finish-to-start links with zero lag and no other restrictions, their early starts can be two. A four-day B then has an early finish of six. Study-guide clarification: the source’s shorthand about copying a finish to successors is correct only when that value governs. With several finish-to-start predecessors, a successor must wait for all of them, so its early start is the maximum applicable predecessor finish plus lag. Do not copy the first predecessor’s value and ignore a later one. The dates remain a deterministic network calculation; probability does not replace this logic.
Source arithmetic, with its assumptions made explicitA: ES 0, duration 2, EF 2. B: FS+0 after A, no other restriction, ES 2, duration 4, EF 6. C can also start at 2 only if no other predecessor or constraint requires it to wait.
Work backward with subtraction and the governing successor
The Q&A encourages learners to complete the forward pass before working backward and calculating floats. Study-guide clarification of the referenced method: in a simple finish-to-start, zero-lag network, initialize the terminal late finish at the chosen project finish, then calculate LS = LF − duration. For a predecessor with several successors, use the smallest permitted successor late start as its late finish. The source’s conversational backward-pass wording is not a complete algorithm. The finish used, lags, calendars and relationship types must be clear. The maximum rule in a forward merge and minimum rule in a backward split express the same need to honor every governing restriction. Mixed relationships require their own start or finish inequalities rather than blindly applying the FS+0 rule to all links.
- Forward · simple FS+0 EF = ES + duration; a merge takes the largest applicable predecessor finish.
- Backward · simple FS+0 LS = LF − duration; a split respects the smallest applicable successor late start.
- Mixed relationships Apply the relevant start or finish constraint and identify the governing bound.
SS+5 and day labels describe different things
The lecturer explains a start-to-start lag of five: if A starts at zero, the successor cannot start before five through that relationship. Study-guide clarification: SS+5 means successor start is at least predecessor start plus five. It does not require the predecessor to finish first, and it does not force the successor to start exactly at five if another restriction requires a later start. A learner also notices an exercise that starts at one. Keep the convention explicit. On an elapsed-time boundary axis, duration equals finish minus start, so EF = ES + duration. If using inclusive day numbers instead, a two-day activity starting on day one occupies days one and two; its last included day is two, so finish-day label = start-day label + duration − one. Under simple FS+0, the successor then begins on the next day label. Do not combine inclusive labels with elapsed-boundary arithmetic. These convention details clarify the Q&A; they do not infer the missing exercise’s full intended convention.
| Convention | Two-day A | FS+0 successor begins |
|---|---|---|
| Elapsed-time boundaries | Start 0; finish boundary 2 | At boundary 2 |
| Inclusive day labels | First day 1; last included day 2 | On day 3 |
Read with careA calendar axis can also be labeled from one while retaining boundary arithmetic. State the convention rather than infer it from a single printed number.
Hard logic is required; soft logic is a chosen order
The final Q&A distinguishes mandatory physical or technical ordering from a preferred sequence. Blood must be collected before the resulting test can be reported, and excavation precedes the relevant foundation work in the source’s examples. These illustrate hard logic: the relationship reflects what the work requires. Preparing presentation slides before writing the script, or writing the script first, illustrates soft logic. Either sequence can be feasible; the team has chosen a preference. A preferred order can still coordinate real work, so review its consequences before changing it. When testing a schedule improvement, explain whether a relationship is a physical necessity or an adjustable planning choice. Do not remove hard logic just to obtain an earlier simulated finish.
Hard logic
- A physical or technical requirement
- Collect the sample before reporting its test result
- Excavation before the dependent foundation work
Soft logic
- A preferred arrangement of feasible work
- Draft the slides, then the script
- Or write the script, then design the slides
Key takeaways
- The simple A-to-B source example uses elapsed time starting at zero.
- Forward merges take the governing maximum; backward splits respect the governing minimum in a simple FS+0 network.
- SS+5 constrains starts and may coexist with another restriction that governs later.
- State the time convention, and distinguish necessary logic from preferred sequencing.