Monte Carlo simulation calculates many possible versions of a schedule. Each trial samples uncertain durations, recalculates the network and records its finish. The result is useful only when shared activities, dependencies and important common risks are represented consistently.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

One trial is a complete possible version of the schedule

The source begins by assigning probability distributions to uncertain activity durations and representing important shared risks. For one trial, software selects possible durations, recalculates the schedule and records the completion time. Repeating this process thousands of times produces many modeled outcomes. Recalculate the network for each trial. Do not add sampled durations along whichever path was critical in the original deterministic plan and assume that path must control every time. The session emphasizes that the controlling path can change. The finish should reflect all the required work and the relationships in that particular trial.

Monte Carlo schedule sequence described in the recording
  1. ModelDurations, relationships and shared risks
  2. SampleOne coherent set of values for a trial
  3. RecalculateEvaluate the full schedule
  4. Record and repeatFinish time and controlling activities

A shared activity keeps the same sampled value within a trial

The lecturer explicitly states that a shared activity must use the same sampled duration wherever it appears within one trial. A single piece of work does not become a different event because two path descriptions include it. If it receives two unrelated draws, the model gives one activity incompatible durations in the same possible project. Study-guide illustration: suppose two routes both include activity A before branching. In a particular trial, A is sampled once as seven days. Every calculation involving A uses those seven days for that trial. The next trial may sample a different value. Seven days and the simplified route are teaching additions, not results supplied by the recording.

Key ideaSample each uncertain activity consistently, then let the network determine how its effects flow through the project.

Relationships and correlated risks answer different questions

Precedence logic describes when work can start or finish relative to other work. Dependence between uncertain durations describes whether their outcomes tend to move together. The recording asks the modeler to represent shared risks; these should be part of the assumptions before interpreting the output. Study-guide clarification: two activities can have different predecessors and still both slow down in the same bad-weather scenario. Drawing their durations independently may miss that common exposure. Conversely, a finish-to-start link does not alone specify a statistical correlation between the two durations. Keep the schedule relationships and the uncertainty dependencies clear, then choose a coherent way to model any important common causes.

Study-guide applicationA weather-sensitive excavation and an outdoor installation may both be affected by the same rainy period. Review a shared weather scenario instead of assuming that one activity’s delay has no relation to the other’s. The actual dependence and duration impact need project evidence.

Read the output as evidence for a decision

The results show a distribution of completion dates and can identify activities that frequently become critical. This helps the team find which work and risks deserve attention. Test a proposed action by changing a justified input or assumption, rerunning the model and comparing the resulting finish distribution. Study-guide clarification: criticality frequency and the size of an activity’s influence are related but different questions. An activity becoming critical often does not, alone, prove which mitigation delivers the largest improvement. Likewise, more trials can reduce sampling noise while leaving weak inputs, missing logic or absent shared risks untouched. Model review remains part of interpreting the forecast.

Key takeaways

  • Each trial samples a coherent project and recalculates its network.
  • One shared activity uses one duration value within a trial.
  • Precedence relationships and correlated duration uncertainty are distinct parts of the model.
  • The distribution and changing criticality support decisions under the model’s assumptions.

Based on the complete 12 November 2026 class recording. Source references use chronological raw-transcript paragraphs; labeled clarifications and practice are study-guide teaching material.