One trial is a complete possible version of the schedule
The source begins by assigning probability distributions to uncertain activity durations and representing important shared risks. For one trial, software selects possible durations, recalculates the schedule and records the completion time. Repeating this process thousands of times produces many modeled outcomes. Recalculate the network for each trial. Do not add sampled durations along whichever path was critical in the original deterministic plan and assume that path must control every time. The session emphasizes that the controlling path can change. The finish should reflect all the required work and the relationships in that particular trial.
- ModelDurations, relationships and shared risks
- SampleOne coherent set of values for a trial
- RecalculateEvaluate the full schedule
- Record and repeatFinish time and controlling activities
Read the output as evidence for a decision
The results show a distribution of completion dates and can identify activities that frequently become critical. This helps the team find which work and risks deserve attention. Test a proposed action by changing a justified input or assumption, rerunning the model and comparing the resulting finish distribution. Study-guide clarification: criticality frequency and the size of an activity’s influence are related but different questions. An activity becoming critical often does not, alone, prove which mitigation delivers the largest improvement. Likewise, more trials can reduce sampling noise while leaving weak inputs, missing logic or absent shared risks untouched. Model review remains part of interpreting the forecast.
Key takeaways
- Each trial samples a coherent project and recalculates its network.
- One shared activity uses one duration value within a trial.
- Precedence relationships and correlated duration uncertainty are distinct parts of the model.
- The distribution and changing criticality support decisions under the model’s assumptions.