Three estimates describe conditions, not just three numbers
PERT stands for Program Evaluation and Review Technique. The optimistic duration, a, represents a short outcome under favorable conditions. The most likely duration, m, represents the duration expected to occur most often. The pessimistic duration, b, represents an unfavorable long outcome. Keep the work scope and units consistent across all three. The most likely value is a mode, not an arithmetic average. That distinction matters because the Q&A sometimes uses “average” conversationally when discussing the middle estimate. Before calculating, confirm what the estimator means and which conditions support the favorable and unfavorable values. A neat formula cannot compensate for three estimates that describe different scopes.
- Optimistic · a Favorable-condition short duration.
- Most likely · m The mode: the duration expected to occur most often.
- Pessimistic · b Unfavorable-condition long duration.
Work through the recording’s 8–10–16 activity
With a equal to eight days, m equal to ten days and b equal to sixteen days, the PERT expected duration is (a + 4m + b) divided by six. Here that is (8 + 40 + 16) divided by six, or about 10.67 days. The most likely value receives four times the weight of either endpoint in this convention. The standard deviation estimate is (b − a) divided by six, giving about 1.33 days. Variance is the square of that estimate, about 1.78 days squared. Duration and standard deviation have units of days; variance has units of days squared. Keep unrounded values during a longer calculation and round only the displayed result.
| Quantity | Formula and substitution | Rounded result |
|---|---|---|
| Expected duration | (a + 4m + b) ÷ 6 = (8 + 4×10 + 16) ÷ 6 | 10.67 days |
| Standard deviation estimate | (b − a) ÷ 6 = (16 − 8) ÷ 6 | 1.33 days |
| Variance estimate | [(b − a) ÷ 6]² = (8 ÷ 6)² | 1.78 days² |
A path calculation needs assumptions about dependence
The lecturer refers to a small network, path expected time and variance, then a normal approximation and Z-score for a deadline. The complete network arithmetic is not spoken. This guide therefore does not invent activities, durations or a numerical deadline probability for that network. Study-guide mathematical extension: for a fixed sequence of additive activity durations, the path’s expected duration is the sum of activity expected durations. If those durations are independent, path variance is the sum of their variances, and path standard deviation is the square root of that total. Adding standard deviations instead is not the same calculation. With dependence, covariance terms matter: Var(sum) equals the sum of variances plus twice the sum of pairwise covariances. A common weather exposure can therefore change the uncertainty of the combined result.
Read with careThe simple variance sum requires independence or zero covariance. Shared causes should not disappear just because the activity estimates were entered separately.
A normal deadline calculation is conditional, and the critical path can change
Study-guide mathematical extension: if the fixed path finish can reasonably be approximated by a normal model, a deadline D can be standardized as Z = (D − path mean) ÷ path standard deviation. A normal cumulative probability then estimates the chance that this path finishes by D. A positive Z places the deadline above the path mean; it does not by itself give the probability without the normal cumulative calculation. The recording’s important warning is that the critical path is not constant. Another path can become controlling when durations vary. Even a sound probability for one fixed path is not automatically the probability that every required path finishes by the deadline. Use the network, shared activities and correlations when assessing the project as a whole; Monte Carlo is introduced next for that broader exploration.
Key takeaways
- PERT expected duration is (a + 4m + b) ÷ 6; m is most likely, not necessarily the mean.
- For 8–10–16 days, expected duration is about 10.67 days and variance about 1.78 days squared.
- Independent-path variance adds variances, then takes a square root for standard deviation.
- A fixed-path probability needs explicit assumptions and does not automatically describe the whole project.