Planning & Controls · 12 November sessionSummary

Module summary · 6 min

From an uncertain duration to an explained commitment

A sound completion forecast connects relevant data, sensible distribution assumptions and correct schedule logic. PERT can clarify an activity or fixed path, while Monte Carlo explores the whole network across many outcomes. Percentiles make the risk behind a proposed date visible.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

First understand the evidence

The five source durations, 3, 4, 4, 5 and 14 days, have a mean of six and a median and mode of four. The long observation shows why an average cannot describe every part of the risk. Spread, skewness and tails add information. Relevant records and explicit expert assumptions help challenge optimism, anchoring and availability. For a normal model with mean ten and standard deviation two, the familiar central bands are eight to twelve, six to fourteen, and four to sixteen days. These are model-specific. The dice Q&A explains repeated sample averages; it does not make every activity or project finish normally distributed.

Then make the model internally consistent

PERT uses optimistic a, most likely m and pessimistic b. With 8–10–16 days, expected duration is about 10.67 days, standard deviation about 1.33 days and variance about 1.78 days squared. A fixed-path probability needs assumptions about dependence and shape. The controlling path can change, so one path’s probability need not be the project probability. Monte Carlo samples coherent durations, preserves important shared risks, recalculates the whole network and records many finishes. A shared activity receives one sample within a trial. Choose triangular, beta-PERT, uniform or normal from evidence: triangular is not equal likelihood everywhere, the PERT mode is not necessarily the mean, and concentration alone does not prove normality.

Finally explain the date and keep the network sound

The source’s illustrative P50, P80 and P95 dates are thirty, 32.5 and 34.9 days. Each describes the proportion of modeled outcomes completed by that threshold. State the chosen confidence level, remaining risk and assumptions, then test feasible actions and update the model as evidence changes. The Q&A returns to the foundations: time-zero forward arithmetic, governing constraints at merges and splits, SS+5, consistent day labels and hard versus soft logic. A probability model operates inside this schedule. It does not excuse incorrect relationships or invent a solution to a network that has not been fully supplied.

  • Can you explain the mean, median, mode and a potential estimation bias?
  • Can you reproduce 8–10–16 PERT arithmetic with correct units?
  • Can you distinguish a fixed-path assumption from changing network criticality?
  • Can you justify a distribution without confusing its mode and mean?
  • Can you preserve shared activity samples and common risks in a trial?
  • Can you explain what remains beyond a proposed completion percentile?
  • Can you state the date convention and governing network relationship?

Based on the complete 12 November 2026 class recording. Source references use chronological raw-transcript paragraphs; labeled clarifications and practice are study-guide teaching material.

Your study checkpoint

Check what stuck

The practice page puts the module under pressure with realistic situations and a knowledge check.