Planning & Controls · 19 November sessionSummary

Module summary · 6 min

A feasible plan connects work, capacity and a clear trade-off

Allocate the work, add the loads in each period and check them against the right resource limit. Use flexibility and priority rules carefully, distinguish smoothing from leveling, and explain the actual finish-date and cost consequences of the proposed plan.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

The assignment and the period must both be feasible

Six hours reviewing drawings plus four hours inspecting the site load one engineer with ten hours on Monday. Eight-hour availability leaves a two-hour overload. The WBS identifies work, the OBS identifies teams and people, and RACI connects the two through different responsibility roles. Ownership alone does not create capacity. A crew’s hours renew by period, a fixed stock of steel is consumed, and the generator example combines an operating limit with fuel availability. Keep the units and planning boundary explicit. For nine workers over twelve weeks, 108 worker-weeks exceed the project’s estimated 101 worker-weeks, but Week 5 still needs fourteen workers against nine available. That five-worker shortage must be resolved at the right time.

The scheduling method depends on the protected constraint

The equipment example gives C priority because it lies on the stated A–B–C–E–G critical path. C and D together need seven compressors against six available. The lecturer reports moving D to Days 11–14 while protecting a twenty-day finish. The full network and period loads are not spoken, so that placement remains a reported example rather than a complete independently checked calculation. Smoothing uses available flexibility while preserving the planned finish. Leveling resolves resource limits and may extend the finish. Leveling is not defined by an inevitable delay or mandatory activity splitting. Adding a worker, machine or shift is a separate change in resource assumptions. Recheck readiness, successors, the whole load and the finish after any proposed move.

The Q&A makes the trade-off concrete

In finance, moving an accountant’s work to Tuesday illustrates leveling when Monday’s report then arrives late. Using a feasible quiet Wednesday can illustrate smoothing. A second person’s support needs its own skills and availability check. The cost effect depends on what changes: paid effort, extra capacity, continuing supervision, rental, overhead or contractual delay exposure. No rates or contract terms are supplied. The AI discussion adds another resource-planning example. Reports and summaries may be faster, while token budgets, quality checks, coordination and human analysis remain. The three-days-to-one-day illustration is not a measured speedup. Plan and check the accepted deliverable, including review and correction.

  • Are responsibility and the required resource units clear?
  • Does each period’s demand fit availability?
  • Can flexible work move without breaking logic or the finish?
  • Is the method protecting the date, the capacity limit or a revised agreement?
  • Which actual costs and assumptions change?
  • Does the revised estimate include verification and acceptance?

Based on the complete 19 November 2026 recording. Source references use chronological raw-transcript paragraphs; labeled clarifications and practice are study-guide teaching material.