- Critical Chain Project Management (CCPM)
A scheduling approach addressing task-duration uncertainty and limited resources through constrained-resource planning and pooled buffer protection.
Review Lesson 1- Common-cause variation
Variation inherent in the way a process usually operates; it does not imply each individual duration is exactly predictable.
Review Lesson 1- Special-cause variation
Variation associated with a disruption outside the process’s usual pattern that calls for investigation.
Review Lesson 1- Time padding
Extra safety time included in an individual task estimate, described in the summary as sometimes driven by fear of delay or pressure.
Review Lesson 1- Student Syndrome
Delaying the start of a task despite having time available.
Review Lesson 1- Parkinson’s Law
The idea that work expands to fill the time allotted to it.
Review Lesson 1- Failure to pass positive variation
An early task completion does not advance subsequent work, so the schedule does not gain from it.
Review Lesson 1- Project buffer
Time protection at the end of the critical chain intended to absorb delays before they affect project completion.
Review Lesson 2- Feeding buffer
Protection against delay on a non-critical path that feeds into the critical chain.
Review Lesson 2- Resource buffer
A signal that a required resource should be ready; the summary explicitly states that it adds no time.
Review Lesson 2- Theory of Constraints (TOC)
An approach focused on identifying and managing bottlenecks to improve the flow of the system.
Review Lesson 3- Bottleneck
A constraint that limits the flow of work through the system.
Review Lesson 3- Resource constraint
A limit on the people, equipment or other resources available to perform scheduled work.
Review Lesson 4- Critical path comparison
The summary’s introductory dependency-based view, contrasted with CCPM’s explicit consideration of dependencies and resource constraints.
Review Lesson 4- Critical chain
The controlling sequence considered with task dependencies and resource constraints in the summary’s CCPM discussion.
Review Lesson 4- Portfolio
Multiple concurrent projects whose combined demand may compete for common resources.
Review Lesson 5- Drum
The common bottleneck that helps set the pace across concurrent projects in the source’s portfolio discussion.
Review Lesson 5- Multitasking
Working across competing tasks; the summary names reducing it and improving focus among CCPM’s intended benefits.
Review Lesson 6