Project, feeding and resource buffers

Identify what each buffer protects and where it belongs. Project and feeding buffers provide time protection; a resource buffer signals readiness without adding time.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

Pool protection where it serves the schedule

The summary’s central buffer idea is to pool safety time instead of hiding contingency within every task. That changes the location and purpose of protection: a buffer protects a project finish or a handoff into the critical chain. Moving protection does not remove uncertainty, and the source gives no rule for how much time to allocate. When studying a buffer, ask two questions: what delay is it meant to absorb, and what part of the schedule is it protecting? Those questions distinguish the three named buffer types without treating them as interchangeable.

Key ideaIdentify the purpose of a buffer before discussing its size.

Match each buffer to its purpose

A project buffer sits at the end of the critical chain and absorbs delays before they affect the project’s planned completion. A feeding buffer protects the chain from delays on a non-critical path that feeds into it. A resource buffer is different: it tells a resource when to be ready and does not add time to the schedule.

The three buffers named in the Week 5 summary
BufferLocation or usePurpose
Project bufferEnd of the critical chainAbsorb delays and protect project completion
Feeding bufferWhere another path feeds the critical chainProtect the chain from delays on that feeding path
Resource bufferReadiness signal for a required resourceHave the resource ready without adding time

Read with careThis table organizes paragraphs 10–12. The source supplies no buffer-sizing formulas, percentages or traffic-light thresholds.

Read a handoff without adding imaginary time

Study-guide example: a specialist is needed for a review on the critical chain. A readiness alert helps the specialist prepare for that work. Calling the alert a resource buffer does not authorize inserting several idle days. If a separate work path must deliver material into the chain, the protection against that path’s delay is a feeding buffer. Protection at the chain’s end is a project buffer. Together, the three roles protect completion, feeding handoffs and resource readiness. Match the protection to the problem rather than adding time wherever an issue appears.

Study-guide exampleSpecialist readiness → resource buffer. Late material from a feeding path → feeding buffer. Delays reaching the project finish → project buffer.

Key takeaways

  • Project buffers protect completion at the end of the critical chain.
  • Feeding buffers protect the chain from delays on paths that join it.
  • Resource buffers signal readiness and add no time.
  • The summary defines buffer roles but does not teach their numerical sizing.

Based on the supplied Week 5 CCPM summary. Paragraph references include the title and headings; examples and practice are study-guide teaching additions.