Planning & Controls · Week 5Worked example

Worked example · illustrative teaching case

Explain CCPM through a shared review resource

A hypothetical teaching case connects resource conflicts, the three buffer roles and a portfolio drum. It illustrates the concepts without inventing a numerical scheduling method.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

Start with the resource conflict

Imagine a team preparing two deliverables. Their preparation tasks are independent, but both deliverables require the same specialist’s full attention for review. A dependency-only view makes both reviews appear ready at once. The team checks availability and agrees a feasible order. The resource conflict exists even though the reviews have no logical dependency on one another. Checking the specialist’s availability makes the plan feasible.

Distinguish protection from readiness

Suppose another path prepares information needed by a review on the critical chain. A feeding buffer would protect that handoff from delay. A project buffer would protect the finish at the end of the chain. A resource buffer would alert the specialist to be ready. The alert adds no time and does not create capacity. Its purpose is to have the specialist ready when the review can begin.

Hypothetical concerns matched to the source’s buffer roles
ConcernBuffer role
A preparation path may arrive late at the chainFeeding buffer
Delays may reach the project’s completionProject buffer
The specialist must be ready for the reviewResource buffer

Expand the view when another project needs the specialist

A second project also needs the same specialist. An independently promised review date can now conflict with the first project’s plan. The combined demand needs a shared discussion rather than separate assumptions. If that specialist is the common bottleneck, it illustrates the drum in the source’s portfolio discussion. The team reviews the combined demand before promising dates. Actual task logic, resource availability and estimates are needed to turn the shared plan into a schedule.

  • Identify the resource conflict that dependencies alone do not resolve.
  • Explain the project buffer, feeding buffer and readiness alert separately.
  • Identify the common bottleneck when several projects compete.
  • State what additional information is needed before calculating a schedule.

Hypothetical study-guide case based on Week 5_Summary.docx, especially paragraphs 2 and 9–23. All project details are teaching additions; the source provides no numerical network, buffer-sizing rule or official assignment template.

Your study checkpoint

Try the decisions on your own project

Write down the objective, deliverables, boundaries, and main constraints, then use the practice page to check your judgment.