Dependencies explain what must precede what
The summary describes CPM through task dependencies and contrasts it with CCPM’s explicit inclusion of resource constraints. A dependency plan establishes which work must finish before another task can begin. That information is essential, but it does not establish that the people or equipment needed by simultaneous tasks are available. Read the source’s statement that CPM considers only dependencies as an introductory comparison. It is not a claim that resource planning cannot be used alongside CPM or that scheduling software cannot analyze resource limits. The teaching distinction here is a dependency-only plan versus one that explicitly incorporates those limits.
Read with careDo not turn the source’s simplified comparison into a universal claim about every CPM workflow or software tool.
Parallel logic may still require sequential work
Study-guide example: two independent review tasks are logically ready together, but each requires the same specialist’s full attention. The absence of a dependency between them does not give the specialist two simultaneous work periods. Their planned timing needs to reflect actual availability. In the summary’s comparison, CCPM incorporates both dependency and resource constraints. That is why the critical-chain perspective can change the plan compared with looking at task logic alone.
Dependency-only view
- Both predecessors are complete
- No logical dependency between the reviews
- Both appear ready to start
Resource-aware view
- Both reviews need the same specialist
- Check the specialist’s availability
- Plan a feasible order
Keep the comparison connected to uncertainty
Resource feasibility is one part of CCPM’s purpose. The other is uncertainty in durations and the use of pooled buffers. A resource-aware sequence can still experience delays, which is why the buffer lesson remains relevant after the team resolves a conflict. When comparing approaches, explain what each plan assumes about resource availability and how uncertainty is protected. Use the actual project’s dependencies, estimates and resource availability to assess its plan.
Key takeaways
- A logical dependency and a resource constraint are different scheduling considerations.
- Tasks ready together may still compete for one resource.
- CCPM explicitly includes both task dependencies and resource constraints.
- The source’s comparison is introductory and includes no calculated network.