Where each part of this case comes from, and how its Week 4 claims stand against the course deck.
The two documents
The case reads version 2.0 of a proposed project charter, dated 22 September 2026 and marked “Reassessed through Week 4”, together with its companion explanation guide. Section numbers refer to those documents. Neither is republished here, and nothing in them is signed, funded or agreed.
Why there is a deck check
The companion guide says its Week 4 alignment was reconstructed from a retained discussion, without reopening the course PDF. That PDF is in this library, so every Week 4 claim was checked against the actual pages and the result is published below. Open the Week 4 lessons →
The earlier version
Version 1 of the same charter is read against Week 3 in its own applied case. This module compares the two rather than replacing it. Open the Week 3 applied case →
The dimensions are connected, and contracting asks what is purchased and how complete the scope is
pp. 40-41
Matches
Fixed price suits defined quantities; the seller's own cost variance does not move the price
pp. 43-49
Matches
Reimbursable pays eligible costs under agreed rules
pp. 65-66
Matches
A capped reimbursable arrangement
p. 64
Beyond the deck: its ceiling device is the not-to-exceed clause on time and material contracts
Sole source needs justification; competition where the market permits
pp. 31-33
Matches
Three comparable quotations
—
Applied choice: the deck sets no number
Risk belongs with the party best able to manage it
p. 98
Matches
Allocating risk contractually does not remove it
pp. 34-36
Consistent, but the guide's own point
A mediator facilitates and does not impose a solution
pp. 104-113
Matches
Arbitration does not automatically precede litigation
pp. 37, 104-105
Matches
PPP and construction-delivery labels are not needed here
pp. 74-100
Consistent
An advance payment is a timing decision, not a contract type
—
Not in the deck: the guide's own distinction
Read with careNo contradiction with the deck was found. The two rows marked beyond the deck are the author's own controls, not misreadings.
Part 01
What version 2 keeps, and what it changes
The project, the numbers and the six-week commitment are unchanged. What moved is control: the sponsor takes back the money decisions, delivery moves to Week 5, and a contracting section appears.
Version 2.0, reassessed through Week 4, proposed for authorization, with the headline figures and the statement that nothing is yet approved.
Charter title block · §1
The carried-forward baseline
Nine commitments the reassessment must not change silently, and the note that the brief's examples do not replace them.
Guide §2
Newly specified controls
The delegation, quotation expectation, escalation times and capped expense arrangement are new proposals in this version.
Guide §2
Evidence basis
The brief controls; the numbers come from recovered work; the Week 4 integration was reconstructed without reopening the deck.
Guide §1 · §11 [C4]
Version comparison
The v1 limits, deadline and risk ratings come from the earlier charter that the Week 3 applied case reads.
v1 Charter §3, §5-7 · Study comparison
Part 02
Weeks 1 to 4 as one line of reasoning
Four course weeks answer four different questions, in order: is this worthwhile, what does success mean, who authorizes it, and how are the delivery commitments arranged.
Four learning stages, the question each answers, and where it appears in the charter.
Guide §3
Charter, contract and plan
Why the charter is not a contract or a detailed plan, and what the assignment's word count buys.
Guide §4
The five dimensions applied
Structure, payment, selection, risk and dispute resolution, answered for this project.
Charter §6 · Guide §8
The course's own five dimensions
The deck names structure, payment, selection, risk and dispute resolution, and stresses that they are connected.
Deck pp. 25, 40-41
Part 03
Scope, objectives and acceptance evidence
The boundary holds because the exclusions are explicit, the six objectives each name their evidence, and acceptance depends on that evidence rather than on delivery volume.
Included activities from requirements to handover, the excluded list, and the rule that a budget balance does not authorize expansion.
Charter §2
The six objectives
O1 to O6 with deadlines relative to authorization and the evidence each names.
Charter §3
Why scope is written this way
The dispatch-note argument, the SMART table, and the carton calculation illustration.
Guide §5
Acceptance
Evidence against every objective, school acceptance, Finance verification and sponsor acceptance.
Charter §9
The course view
A fixed price depends on a statement of work detailed enough to price, or claims and disputes follow.
Deck pp. 46-47
Part 04
Budget, gates and bounded authority
The ceiling, the gates and the delegated limits work together: the manager can act, the sponsor keeps the money decisions, and each gate is a decision rather than a date that passes.
The four allowances, the 15% contingency inside the ceiling, the per-book indicator and the six gates.
Charter §4
Authority
Delegated decisions, reserved decisions, weekly reporting, escalation windows and the separation of Finance.
Charter §5
Why the numbers are defensible
Logical estimating rather than market accuracy, the USD 8,400 and USD 9,400 worked forecasts, and the refusal of invented return figures.
Guide §6
Why authority is bounded
The aggregate threshold, the two USD 600 orders, the escalation clock and separated responsibilities.
Guide §7
Part 05
Structure, selection and payment
Three of the five contracting decisions, applied: who holds which agreement, how suppliers are chosen, and where the price is fixed rather than reimbursed.
Structure, selection, payment, risk allocation and dispute resolution as the charter proposes them.
Charter §6
Structure and payment explained
The purchasing principal, the NGO's limited role, fixed prices after definition, the capped expense arrangement and the advance-payment distinction.
Guide §8.1-8.2
Selection explained
Conformity before price, three comparable quotations as a proportionate control, and documented exceptions in a thin market.
Guide §8.3
The course view
Structure as who does what; prequalification, sole sourcing and open or limited bidding; fixed price for defined scope; reimbursable for allowable costs, with the not-to-exceed clause on time and material.
Deck pp. 26-33, 43-49, 61-66
Part 06
Risk allocation and the top three risks
Each party carries what it can control, and the three named risks carry owners and triggers instead of ratings, so someone knows what to watch and when to act.
Inspection points, replacement duties, transit responsibility, delivery dates, proof of receipt and variation procedures, and the limit of allocation.
Charter §6
The three risks
R1 delivery disruption, R2 cost exceedance with the USD 8,000 and USD 9,200 triggers, R3 suitability and access, each with an owner.
Charter §7
Why these three, and how they are written
Cause, event and effect with an owner, preventive action and trigger; the ranking as a proposal to validate; why customs is out.
Guide §9
Allocation and its limits
Conformity, transit and funding responsibilities, and the reminder that allocation does not remove exposure.
Guide §8.4
The course view
Risk as an uncertain event affecting objectives, the contracting question of which party handles which risk, and the principle that risk belongs with the party best able to manage it.
Deck pp. 34-36, 97-98
Part 07
Disputes, stakeholders and explaining the submission
The charter proposes an escalation route that starts with a letter and ends where the real contracts decide, keeps beneficiaries in the stakeholder list, and finishes with an explanation the author can defend out loud.
Written notice, negotiation, sponsor escalation, consensual mediation, and formal routes left to the actual contracts with local advice.
Charter §6
Mediation and arbitration
The mediator facilitates rather than decides; arbitration submits the dispute to an arbitrator; neither automatically precedes litigation.
Guide §8.5 · its references [R4], [R5]
Stakeholders
Eight roles with what each controls, and the argument for keeping beneficiaries in the list.
Charter §8 · Guide §9
Explaining the submission
Five rehearsed questions and a concise spoken explanation of what completion means.
Guide §10
The course view
Negotiation, mediation, arbitration and litigation; the contract names the route, the jurisdiction and the governing law; PPP models belong to public infrastructure.
Deck pp. 37-39, 86-100, 104-115
Source appendix
Where these documents need a careful reading
Read with care
A reconstructed reassessment
The guide states that the Week 4 course PDF and the two earlier documents were not reopened, so its alignment is reconstructed rather than verified slide by slide. The check above is this module's own work, made because the deck is in this library.
A recovered baseline
The numbers are carried forward from recovered earlier work rather than from the submitted Week 2 document.
Newly specified controls
The USD 1,000 delegation, the quotation expectation, the escalation windows and the capped expense arrangement are new proposals in this version. The guide is explicit that they must not be described as previously approved sponsor policies.
An academic scenario
The country, the schools, the NGO, the suppliers, the prices and the sponsor are planning assumptions. No field work, market research or supplier interview was carried out, and no signature exists.
Illustrative arithmetic
The 40-out-of-50 carton example, the USD 8,400 and USD 9,400 forecasts and the USD 4.60 and USD 4.00 per-book figures illustrate method. They are not forecasts, and the per-book figures are not returns.
The guide's external references
Its five references, to a PMI conference paper, two US federal acquisition regulation sections and two WIPO explanations, are the guide's own sources, checked by its author on 22 September 2026 and used for terminology only. They are not claimed to govern a Cambodian project, and this module does not restate them as law.
Not legal advice
The charter leaves arbitration and litigation arrangements to the actual contracts with appropriate local advice, and claims no enforceability. Nothing here is legal or financial advice.
A version, not a correction
Version 1 is not wrong; it is the Week 3 reading of the same project. This case compares the two rather than replacing the earlier one.
Checked against the charter, the companion guide and the Week 4 deck.
What not to take away
The case parts actively work against these misreadings:
A reassessment may quietly move the baseline it inherited.
A forecast below the ceiling needs no approval.
A purchasing limit applies to each order rather than to the supplier in total.
Contingency is extra money on top of the ceiling.
Cost per book is a return on investment.
A coordinator who arranges delivery can commit the client's money.
The cheapest conforming-looking bid is the cheapest bid.
An advance payment is a type of contract.
Allocating a risk to a supplier removes it from the project.
Stakeholders without formal power can be left out of the list.
A charter can promise a measured improvement in literacy.
Mediation and arbitration are two names for the same thing.
Study-guide synthesis; each item is addressed in the parts.