Case source guide

Applied case: a charter reassessed through Week 4

Where each part of this case comes from, and how its Week 4 claims stand against the course deck.

The two documents

The case reads version 2.0 of a proposed project charter, dated 22 September 2026 and marked “Reassessed through Week 4”, together with its companion explanation guide. Section numbers refer to those documents. Neither is republished here, and nothing in them is signed, funded or agreed.

Why there is a deck check

The companion guide says its Week 4 alignment was reconstructed from a retained discussion, without reopening the course PDF. That PDF is in this library, so every Week 4 claim was checked against the actual pages and the result is published below. Open the Week 4 lessons

The earlier version

Version 1 of the same charter is read against Week 3 in its own applied case. This module compares the two rather than replacing it. Open the Week 3 applied case

Case map · Charter, Guide and Deck
Case partCharterGuideCourse lessons applied
1 · The reassessmentTitle block, §1§1-2Module 3: what a charter is, delegation
2 · Weeks 1 to 4§6§3-4, §8Week 4: dimensions of contracting
3 · Scope and objectives§2-3, §9§5Week 4: fixed price and the statement of work
4 · Budget and authority§4-5§6-7Module 3: delegation of authority
5 · Structure and payment§6§8.1-8.3Week 4: parties, dimensions, fixed price, variable price
6 · Risk allocation§6-7§8.4, §9Week 4: risk dimension, PPP risk principle
7 · Disputes and stakeholders§6, §8§8.5, §9-10Week 4: dispute resolution, PPP; Module 3: stakeholders
Week 4 claims checked against the deck
Claim in the charter or guideDeckResult
The five contracting dimensions and their orderp. 25Matches
The dimensions are connected, and contracting asks what is purchased and how complete the scope ispp. 40-41Matches
Fixed price suits defined quantities; the seller's own cost variance does not move the pricepp. 43-49Matches
Reimbursable pays eligible costs under agreed rulespp. 65-66Matches
A capped reimbursable arrangementp. 64Beyond the deck: its ceiling device is the not-to-exceed clause on time and material contracts
Sole source needs justification; competition where the market permitspp. 31-33Matches
Three comparable quotations—Applied choice: the deck sets no number
Risk belongs with the party best able to manage itp. 98Matches
Allocating risk contractually does not remove itpp. 34-36Consistent, but the guide's own point
A mediator facilitates and does not impose a solutionpp. 104-113Matches
Arbitration does not automatically precede litigationpp. 37, 104-105Matches
PPP and construction-delivery labels are not needed herepp. 74-100Consistent
An advance payment is a timing decision, not a contract type—Not in the deck: the guide's own distinction

Read with careNo contradiction with the deck was found. The two rows marked beyond the deck are the author's own controls, not misreadings.

Part 01

What version 2 keeps, and what it changes

The project, the numbers and the six-week commitment are unchanged. What moved is control: the sponsor takes back the money decisions, delivery moves to Week 5, and a contracting section appears.

Open the case part
The charter's identity and purpose

Version 2.0, reassessed through Week 4, proposed for authorization, with the headline figures and the statement that nothing is yet approved.

Charter title block · §1
The carried-forward baseline

Nine commitments the reassessment must not change silently, and the note that the brief's examples do not replace them.

Guide §2
Newly specified controls

The delegation, quotation expectation, escalation times and capped expense arrangement are new proposals in this version.

Guide §2
Evidence basis

The brief controls; the numbers come from recovered work; the Week 4 integration was reconstructed without reopening the deck.

Guide §1 · §11 [C4]
Version comparison

The v1 limits, deadline and risk ratings come from the earlier charter that the Week 3 applied case reads.

v1 Charter §3, §5-7 · Study comparison

Part 02

Weeks 1 to 4 as one line of reasoning

Four course weeks answer four different questions, in order: is this worthwhile, what does success mean, who authorizes it, and how are the delivery commitments arranged.

Open the case part
The weeks-to-charter map

Four learning stages, the question each answers, and where it appears in the charter.

Guide §3
Charter, contract and plan

Why the charter is not a contract or a detailed plan, and what the assignment's word count buys.

Guide §4
The five dimensions applied

Structure, payment, selection, risk and dispute resolution, answered for this project.

Charter §6 · Guide §8
The course's own five dimensions

The deck names structure, payment, selection, risk and dispute resolution, and stresses that they are connected.

Deck pp. 25, 40-41

Part 03

Scope, objectives and acceptance evidence

The boundary holds because the exclusions are explicit, the six objectives each name their evidence, and acceptance depends on that evidence rather than on delivery volume.

Open the case part
Scope and exclusions

Included activities from requirements to handover, the excluded list, and the rule that a budget balance does not authorize expansion.

Charter §2
The six objectives

O1 to O6 with deadlines relative to authorization and the evidence each names.

Charter §3
Why scope is written this way

The dispatch-note argument, the SMART table, and the carton calculation illustration.

Guide §5
Acceptance

Evidence against every objective, school acceptance, Finance verification and sponsor acceptance.

Charter §9
The course view

A fixed price depends on a statement of work detailed enough to price, or claims and disputes follow.

Deck pp. 46-47

Part 04

Budget, gates and bounded authority

The ceiling, the gates and the delegated limits work together: the manager can act, the sponsor keeps the money decisions, and each gate is a decision rather than a date that passes.

Open the case part
Budget and schedule

The four allowances, the 15% contingency inside the ceiling, the per-book indicator and the six gates.

Charter §4
Authority

Delegated decisions, reserved decisions, weekly reporting, escalation windows and the separation of Finance.

Charter §5
Why the numbers are defensible

Logical estimating rather than market accuracy, the USD 8,400 and USD 9,400 worked forecasts, and the refusal of invented return figures.

Guide §6
Why authority is bounded

The aggregate threshold, the two USD 600 orders, the escalation clock and separated responsibilities.

Guide §7

Part 05

Structure, selection and payment

Three of the five contracting decisions, applied: who holds which agreement, how suppliers are chosen, and where the price is fixed rather than reimbursed.

Open the case part
Procurement and contracting approach

Structure, selection, payment, risk allocation and dispute resolution as the charter proposes them.

Charter §6
Structure and payment explained

The purchasing principal, the NGO's limited role, fixed prices after definition, the capped expense arrangement and the advance-payment distinction.

Guide §8.1-8.2
Selection explained

Conformity before price, three comparable quotations as a proportionate control, and documented exceptions in a thin market.

Guide §8.3
The course view

Structure as who does what; prequalification, sole sourcing and open or limited bidding; fixed price for defined scope; reimbursable for allowable costs, with the not-to-exceed clause on time and material.

Deck pp. 26-33, 43-49, 61-66

Part 06

Risk allocation and the top three risks

Each party carries what it can control, and the three named risks carry owners and triggers instead of ratings, so someone knows what to watch and when to act.

Open the case part
Risk allocation in the contracts

Inspection points, replacement duties, transit responsibility, delivery dates, proof of receipt and variation procedures, and the limit of allocation.

Charter §6
The three risks

R1 delivery disruption, R2 cost exceedance with the USD 8,000 and USD 9,200 triggers, R3 suitability and access, each with an owner.

Charter §7
Why these three, and how they are written

Cause, event and effect with an owner, preventive action and trigger; the ranking as a proposal to validate; why customs is out.

Guide §9
Allocation and its limits

Conformity, transit and funding responsibilities, and the reminder that allocation does not remove exposure.

Guide §8.4
The course view

Risk as an uncertain event affecting objectives, the contracting question of which party handles which risk, and the principle that risk belongs with the party best able to manage it.

Deck pp. 34-36, 97-98

Part 07

Disputes, stakeholders and explaining the submission

The charter proposes an escalation route that starts with a letter and ends where the real contracts decide, keeps beneficiaries in the stakeholder list, and finishes with an explanation the author can defend out loud.

Open the case part
Dispute resolution as proposed

Written notice, negotiation, sponsor escalation, consensual mediation, and formal routes left to the actual contracts with local advice.

Charter §6
Mediation and arbitration

The mediator facilitates rather than decides; arbitration submits the dispute to an arbitrator; neither automatically precedes litigation.

Guide §8.5 · its references [R4], [R5]
Stakeholders

Eight roles with what each controls, and the argument for keeping beneficiaries in the list.

Charter §8 · Guide §9
Explaining the submission

Five rehearsed questions and a concise spoken explanation of what completion means.

Guide §10
The course view

Negotiation, mediation, arbitration and litigation; the contract names the route, the jurisdiction and the governing law; PPP models belong to public infrastructure.

Deck pp. 37-39, 86-100, 104-115

Source appendix

Where these documents need a careful reading

Read with care

A reconstructed reassessment

The guide states that the Week 4 course PDF and the two earlier documents were not reopened, so its alignment is reconstructed rather than verified slide by slide. The check above is this module's own work, made because the deck is in this library.

A recovered baseline

The numbers are carried forward from recovered earlier work rather than from the submitted Week 2 document.

Newly specified controls

The USD 1,000 delegation, the quotation expectation, the escalation windows and the capped expense arrangement are new proposals in this version. The guide is explicit that they must not be described as previously approved sponsor policies.

An academic scenario

The country, the schools, the NGO, the suppliers, the prices and the sponsor are planning assumptions. No field work, market research or supplier interview was carried out, and no signature exists.

Illustrative arithmetic

The 40-out-of-50 carton example, the USD 8,400 and USD 9,400 forecasts and the USD 4.60 and USD 4.00 per-book figures illustrate method. They are not forecasts, and the per-book figures are not returns.

The guide's external references

Its five references, to a PMI conference paper, two US federal acquisition regulation sections and two WIPO explanations, are the guide's own sources, checked by its author on 22 September 2026 and used for terminology only. They are not claimed to govern a Cambodian project, and this module does not restate them as law.

Not legal advice

The charter leaves arbitration and litigation arrangements to the actual contracts with appropriate local advice, and claims no enforceability. Nothing here is legal or financial advice.

A version, not a correction

Version 1 is not wrong; it is the Week 3 reading of the same project. This case compares the two rather than replacing the earlier one.

Checked against the charter, the companion guide and the Week 4 deck.

What not to take away

The case parts actively work against these misreadings:

  • A reassessment may quietly move the baseline it inherited.
  • A forecast below the ceiling needs no approval.
  • A purchasing limit applies to each order rather than to the supplier in total.
  • Contingency is extra money on top of the ceiling.
  • Cost per book is a return on investment.
  • A coordinator who arranges delivery can commit the client's money.
  • The cheapest conforming-looking bid is the cheapest bid.
  • An advance payment is a type of contract.
  • Allocating a risk to a supplier removes it from the project.
  • Stakeholders without formal power can be left out of the list.
  • A charter can promise a measured improvement in literacy.
  • Mediation and arbitration are two names for the same thing.

Study-guide synthesis; each item is addressed in the parts.