The submission in one line
The charter proposes a book donation and distribution initiative: 2,000 usable, school-approved books for four primary schools in one underserved rural Cambodian district, within six weeks of written authorization and a funding ceiling of USD 9,200. Books are sourced inside Cambodia through a local NGO, then donated. This is version 2.0, dated 22 September 2026 and marked “Reassessed through Week 4”. Its status is proposed for sponsor authorization.
- The purpose is stated as improving access to suitable reading materials, not moving stock.
- Approval would set the scope, objectives, funding limits and delegated authority, and appoint the project manager. It would not be a supplier contract.
- The charter states plainly that no funding release, partnership or supplier commitment is already approved.
Read with careCambodia, the four schools, the NGO, the suppliers, the prices and the sponsor are planning assumptions for an academic scenario. Nothing here is a verified field finding, a quotation or a signed agreement.
The baseline that must not change silently
The companion guide opens with the commitments carried forward from the earlier definition of the same project. They are listed so that a reassessment cannot quietly move them, and the site treats them the same way.
| Commitment | Why the guide says it matters |
|---|---|
| 2,000 usable, approved books | The target is accepted educational material, not purchased or dispatched stock |
| Four primary schools in one rural district | Keeps the original manageable delivery model; the identities still need confirming |
| Needs-based allocation totalling 2,000 | The earlier work did not fix 500 books per school, so equal allocation must not be invented |
| Six weeks from written authorization | Gives the deadline a clear starting event that an informal restart cannot hide |
| USD 8,000 base plus USD 1,200 contingency | Preserves the USD 9,200 ceiling, with contingency already inside it |
| In-country sourcing through a local NGO | Keeps budget and schedule consistent; international shipping is not added |
| Storage and volunteer support in kind | Makes the low cash estimate conditional on confirmed contributions |
| At least 80% carton reuse or recovery by Week 6 | Preserves the original sustainability objective, its timing and its meaning |
| Handover, custodians, pupil access and client acceptance | Connects delivery to a usable result and a documented closure |
What the reassessment changed
Comparing the two versions of the same charter shows where the thinking moved. The numbers did not change at all: the same 2,000 books, four schools, six weeks and USD 9,200, built from the same USD 6,000, 400, 1,000 and 600 allowances.
| Decision | Version 1 | Version 2 |
|---|---|---|
| Contingency release | The PM could release USD 300 per risk event, USD 600 in total | Reserved to the sponsor in full |
| Budget transfers | The PM could move USD 400 between allowances | Reserved to the sponsor in full |
| Purchasing limit | USD 1,000 per procurement package | USD 1,000 per supplier in aggregate; splitting orders is prohibited |
| Delivery and handover | By the end of Week 6 | By the end of Week 5, with Week 6 for verification and closure |
| Carton objective | Reuse, recovery or recycling | Reuse or recovery for reuse only; unsafe cartons excluded |
| Risks | Classified internal or external, rated medium or high | Provisional priorities with named owners and triggers, to be reviewed in Week 1 |
| Contracting | Not addressed | A full section: structure, selection, payment, risk allocation and disputes |
Control moved toward the sponsor
The clearest change is financial. Version 1 gave the project manager small amounts of discretion over contingency and budget transfers. Version 2 removes both and keeps the manager's authority operational instead: sequencing the work, approving routine purchases within a limit, rejecting nonconforming goods and pausing unsafe or unauthorized work.
- Contingency use and transfers between allowances now require sponsor approval, whatever the amount.
- The purchasing limit became an aggregate figure per supplier, so repeated small orders cannot add up past it.
- Nonstandard contract terms and dispute settlements were added to the reserved list.
- Finance pays only against authorized commitments and supporting evidence, separately from the manager's own verification.
Key ideaAuthority is not one number. This version separates what the manager may decide, what the sponsor reserves, and who checks the evidence before money moves.
Applied choiceThe USD 1,000 aggregate limit, the one-working-day escalation and the two-working-day response target are the author's design choices for this project. They are proposals, not course rules or an organization's approved policy.
Delivery moved a week earlier
In version 1 the objective was delivery and signed receipt by the end of Week 6, and Week 5 appeared only as a target inside the transport risk response. Version 2 promotes it: delivery and handover are due by the end of Week 5, and Week 6 carries verification, carton recovery, cost reconciliation and acceptance.
Key ideaWeek 5 is an intermediate control inside the original six-week commitment, not a new final deadline. The guide is explicit that Week 6 is reserved for verification and closure, not for routine late delivery.
What the reassessment does not claim
The guide is unusually careful about its own evidence, and the module keeps that care visible. The assignment brief is the controlling requirement, the numbers come from recovered earlier work, and the Week 4 integration was reconstructed from a retained discussion rather than a fresh reading of the course deck.
- It calls itself a reconstructed reassessment, not a tracked-change comparison or a verified slide-by-slide alignment.
- The newly specified controls must not be described as previously approved sponsor policies.
- The brief's own illustrations, such as three schools or six months, are examples of how to write objectives, not substitutes for the project's assumptions.
Read with careBecause the deck itself is in this library, the source guide for this case re-checks every Week 4 claim against the actual pages and reports the result. That check is this module's work, not the guide's.
Key takeaways
- Version 2 keeps every number and the six-week commitment, and changes how the project would be controlled.
- All contingency use and budget transfers moved back to the sponsor.
- The purchasing limit is now an aggregate per supplier, so orders cannot be split past it.
- Delivery and handover moved to Week 5 so that Week 6 can verify and close.
- The reassessment states its own evidence limits rather than implying verified alignment.