Project Management · Module 4Applied casePart 6

Applied case · Part 06 · 15 min

Risk allocation and the top three risks

Each party carries what it can control, and the three named risks carry owners and triggers instead of ratings, so someone knows what to watch and when to act.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

Who carries what

The agreements are to specify inspection points, replacement duties, transit responsibility, delivery dates, proof of receipt and written variation procedures. That turns a general intention into an allocation each party can actually manage.

  • Supplier Conformity of the books: complete, legible, undamaged and matching the approved educational requirements.
  • Carrier Agreed handling and transit obligations, including delivery dates and proof of receipt.
  • Client Timely decisions and funding, which are the two things only the sponsor can supply.
  • NGO Local readiness: consultation, inspection before dispatch and verification of access after handover.

Allocation does not remove the risk

The guide refuses the comfortable reading of a contract clause. A supplier may still deliver late or fail to replace defects in time, and the project still suffers the delay. The manager's duty to monitor warning signs and plan recovery survives every allocation.

Key ideaThe charter says the same thing in its own words: contract allocation does not remove the manager's duty to monitor performance, or the project's exposure to disruption.

How the risks are written now

Version 1 classified each risk as internal or external and rated likelihood and impact. Version 2 drops the ratings and gives each risk an owner, a preventive action and a trigger, while stating openly that the ranking is provisional and must be reviewed with the NGO in Week 1.

  • The guide's reason: each risk is written as cause, possible event and effect, then linked to an owner, a preventive action and a trigger, which makes it actionable.
  • Its test for a weak risk statement: “There may be delays” has little management value unless someone knows what to monitor and when to intervene.

Read with careThe ranking is a reasoned proposal, not a numerical forecast. The charter says the likelihood and impact must be reviewed with the NGO, and that the ordering is not based on field statistics.

R1 · Delivery disruption or damage

Route disruption, vehicle failure or poor handling could delay delivery or damage books, preventing the Week 5 handover. Every school depends on physical receipt, which is why this risk is first.

  • Owner: the project manager, supported by the carrier and the NGO.
  • Prevention: confirm route access and receiving dates, use protective packaging, identify an alternative carrier.
  • Trigger: failure to confirm dispatch readiness by the end of Week 3.
  • Response: use the Week 5 correction window and seek sponsor approval for any additional cost. Unsafe transport will not proceed.

R2 · Costs exceed the available funding

Book-price changes, omitted transport charges or the loss of assumed in-kind support could exhaust the contingency. The project cannot simply reduce the 2,000-book commitment to balance the books.

  • Owner: the project manager, supported by Finance.
  • Prevention: complete quotations, confirmed in-kind contributions, a weekly forecast of total cost.
  • Response: compliant supplier alternatives, without reducing educational quality.

Worked exampleA forecast above USD 8,000 triggers a contingency review. A forecast above USD 9,200 requires an immediate sponsor decision before the affected commitments are made.

Applied choiceBoth trigger levels are the author's design. They line up with the base estimate and the ceiling rather than with any course or industry threshold.

R3 · Books that do not fit, or cannot be reached

Inadequate consultation could produce unsuitable languages or reading levels, and weak school ownership could leave the books unused. This risk threatens the project's purpose even when delivery is punctual, which is exactly why it sits alongside the delivery and cost risks.

  • Owner: the NGO coordinator, accountable to the project manager.
  • Prevention: teacher approval before purchase, verified samples, needs-based allocation, named custodians and agreed access.
  • Trigger: missing approval at the Week 1 gate, or absent receiving arrangements, blocks the affected purchase or dispatch.

Key ideaA project can hit a transport target and still fail. R3 is the risk that the books arrive and do nothing.

Why customs is not on the list

The guide answers an obvious challenge. Customs clearance would be a natural top risk for a donation project, but international shipment is excluded from this scope, so it cannot be one here. A generic example from the brief should not override the actual sourcing model; if overseas procurement were ever proposed, both the scope and the risk assessment would need reconsidering.

Key takeaways

  • Conformity sits with the supplier, transit with the carrier, funding and decisions with the client.
  • A contract clause reallocates a risk; it does not make it disappear.
  • Version 2 replaced likelihood and impact ratings with owners and triggers.
  • Each trigger names the moment someone must act, not just the thing to fear.
  • The three risks cover delivery, affordability and usefulness, and customs is excluded by scope.

Study explanation of a proposed academic charter, version 2, and its companion guide, read against the supplied Week 4: The Project Contract course deck. Open the source notes above to see which document each claim comes from.